DRAINS ANALYSIS RESULTS
MINOR STORMS
DRAINS results prepared 20 January, 2011 from Version 2010.10
PIT / NODE DETAILS Version 8
Name Max HGL Max Pond Max Surface Max Pond Min Overflow Constraint
HGL Flow Arriving Volume Freeboard (cu.m/s)
(cu.m/s) (cu.m) (m)
N6 11.12 0.85
N3 8.11 0
SUB-CATCHMENT DETAILS
Name Max Paved Grassed Paved Grassed SUP P. Due to Storm
Flow Q - Max Q Max Q Tc Tc Tc
(cu.m/s) (cu.m/s) (cu.m/s) (min) (min) (min)
Catl 0.85 0.804 0.047 15 30 0 AR&R 10 year, 20 minutes storm, average 128 mm/h, Zone .3
Outflow Volumes for Total Catchment (1.87 impervious + 0.46 pervious = 2.33 total ha)
Storm Total Rainfall Total Runoff Impervious Runoff Pervious Runoff
cu.m cu,m (Runoff %) cu.m (Runoff %) cu.m (Runoff %)
AR&R 5 year, 5 minutes storm, average 202 mm/h, Zone 3 391.71 301.50 (77.0%) 296.23 (94.1%) 5.27 (6.9%)
AR&R 5 year, 10 minutes storm, average 156 mm/h, Zone 3 605.02 482.98 (79.8%) 467.73 (96.2%) 15.25 (12.9%)
AR&R 5 year, 20 minutes storm, average 115 mm/h, Zone 3 892.02 734.48 (82.3%) 698.47 (97.4%) 36.01 (20.6%)
AR&R 5 year, 30 minutes storm, average 94.2 mm/h, Zone 3 1096.02 914.99 (83.5%) 862.49 (97.9%) 52.50 (24.4%)
AR&R 5 year, 1 hour storm, average 64.7 mm/h, Zone 3 1505.57 1271.35 (84.4%) 1191.77 (98.5%) 79.59 (27.0%)
AR&R 5 year, 2 hours storm, average 42.8 mm/h, Zone 3 1991.91 1654.79 (83.1%) 1582.79 (98.8%) 72.00 (18.4%)
AR&R 10 year, 5 minutes storm, average 223 mm/h, Zone 3 432.43 336.72 (77.9%) 328.97 (94.6%) 7.76(9.2%)
AR&R 10 year, 10 minutes storm, average 173 mm/h, Zone 3 670.95 543.40 (81.0%) 520.74 (96.5%) 22.67 (17.2%)
AR&R 10 year, 20 minutes storm, average 128 mm/h, Zone 3 992.85 833.22 (83.9%) 779.54 (97.7%) 53.68 (27.6%)
AR&R 10 year, 30 minutes storm, average 105 mm/h, Zone 3 1221.67 1037.98 (85.0%) 963.52 (98.1% 74.47 (31.1%)
AR&R 10 year, 1 hour storm, average 72.3 mm/h, Zone 3 1682.42 1441.94 (85.7%) 1333.96 (98.6%) 107.99 (32.7%)
AR&R 10 year, 2 hours storm, average 48.4 mm/h, Zone 3 2252.54 1901.79 (84.4%) 1792.33 (99.0%) 109.46 (24.8%)
PIPE DETAILS
Name Max Q Max V Max U/S Max D/S Due to Storm
(cu.m/s) (m/s) HGL (m) HGL (m)
Pipe3 0.85 2.4 11.116 11.066 AR&R 10 year, 20 minutes storm, average 128 mm/h, Zone 3
Pipel 0.425 6 8.905 8.105 AR&R 10 year, 1 hour storm, avers e 72.3 mm h, Zone 3
CHANNEL DETAILS
Name Max Q Max V Chainage Max Due to Storm
cu.m/s) (m/s) (m) HGL (m)
DETENTION BASIN DETAILS
Name Max WL MaxVol Max Q Max Q Max Q
Total Low Level High Level
Basin2 9.98 628.9 0.425 0.425 0
CONTINUITY CHECK for AR&R 10 year, 20 minutes storm, average 128 mm/h, Zone 3
Node Inflow Outflow Storage Change Difference
(cu.m) (cu.m) (cu.m) %
N6 833.22 833.22 0 0
Basin2 833.22 827.51 -11.2 2
N3 726.62 726.62 0 01 1
20/01/2011 K:\AA - Great Plains Jobs\4400 (Bunnings Noosa)\02 (Civil)\Admin\WSUD\Admin\4400-02(DRAINS Modelling Results)
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
OPW11/0023 Development Application part 2 of 2 Planning Report and Plans 178 Eumundi Noosa Road NoosavilleRelated documentApplication case desk ↗
About this file
- File size
- 70.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.