SUPERCEDED Decision Notice - Approved by Delegation of Authority MCU23 0094, OPW23 0113 & RAL23 0014 [As Published] · MCU23/0094
c. Works programme identifying key components of the works and their respective
durations.
d. Establishment of a communication protocol with the general public, adjoining owners,
emergency services and local businesses to advise of agreed construction times,
impacts on traffic and services and other relevant issues.
e. Include a post out to the local residents and businesses advising of the proposed
development, the expected time frames and the site contact details.
f. Include signage in prominent locations on the boundaries of the site advising of the
proposed development, the expected time frames and the site contact details.
g. Identification of complaint management procedures including:
i. Contact details for the on-site manager
ii. Dispute resolution procedures
h. For haulage operations involving significant volumes of fill material or excavated
material being transported onto or off the site: details on the location of external fill
sites/sources, the haulage route, type of vehicle to be utilised during filling operations
and frequency of usage. NB any damage to the existing road system as a result of
haulage operations shall be fully repaired at the applicant’s expense.
13. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
14. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
DURING CONSTRUCTION
Engineering
15. The developer must meet any costs to repair damage to any Council asset during
construction, where damage is a result of the development works. Damage to assets must
be repaired immediately where it creates a hazard to the community. In circumstances where
the damage does not create a hazard to the community, it must be repaired immediately on
completion of the works associated with the development.
16. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
who is independent of the Developer and Principal Contractor, and they must certify that all
works conform to the Operational Works permit. Where municipal works are involved, such
confirmation must be submitted for the respective hold points prior to any site inspection by
Council Officers.
17. All works must be constructed and work procedure undertaken in accordance with:
a. The approved plans/documents and conditions detailed in this Decision Notice
b. All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines
c. The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site
Roadworks (External Roadworks & Road Widening Works)
18. All pavement widening or construction of new pavement must join neatly to the existing
pavement so that there are no irregularities in line or level resulting at or adjacent to the join
for the length of the construction. Where necessary the existing pavement must be brought
to a satisfactory standard to allow for the above.
Page 16 of 28
Document Set ID: 22759072
Version: 6, Version Date: 11/01/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERCEDED Decision Notice - Approved by Delegation of Authority MCU23 0094, OPW23 0113 & RAL23 0014 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 245 KB (small file)
- File type
No other editions are linked here.