2.2.1.4 Severe Storm
A severe storm assessment has been completed, which has assessed the 1% (2100) AEP, assuming stormwater network is 100% blocked.
Figure 2.6 highlights the flood depths in this event, which highlights flow depth reach a maximum 0.7m (in upstream pit), with flow depths
in channel being generally less than 0.5m. This mapping also highlights that flows are contained within the designated flow path and do not
break out and impact the proposed development. Downstream of the site it is seen that flows are contained within the cul-de-sac of Serenity
Plan and designated footpath, and do not impact the transformer pad or adjacent properties.
FIGURE 2.6: EXCERPT OF SEVERE STORM DEPTH MAP - 1% (2100) AEP FULLY BLOCKED
DocumentNOOSA
Set ID:CALILE I BBNE01676-0001-REP-001-1
23806878 13
Version: 0, Version Date: 01/01/1900
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.