SUPERSEDED NEGOTIATED - OPW25 0042 - REFERENCE DOCUMENT (As Published)

of 180

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file (18.6 MB): the original may take a few minutes to open or download. The page text below is quick to read.

Original PDF page 165, section 1. The text section number identifies this passage in the reader.

     Traffic Management Plan – 25040286

            Conduct on the spot maintenance/repairs as required.
            When traffic controllers are on the job, ensure they remain in place at all times. Relieve controllers as
              necessary to ensure attentiveness is retained.
            During breaks or changes in work activities remove or cover any signs that do not apply (e.g. PREPARE
              TO STOP, Workers symbolic).
            Re-position signs and devices as required by work processes throughout the day and keep records of
              any changes.

          10.1.3 Closing down each day

          Conduct a pre-close down inspection, allowing time for any appropriate maintenance works.
          Remove any unnecessary signage (e.g. Prepare to Stop, Symbolic Workers).
          Replace any unnecessary signage with appropriate delineation.
          Install barriers and lights where required.
          Drive through site and confirm all signs and devices are operating correctly with no misleading visual
               cues.
          Record details of inspection and any changes made to layout.
     Regular monitoring of signs and devices to take place with regular periodic checks. Should any signs or
     devices show evidence of Vandalism or tampering the sign or devices is to be reinstated as per TGS. If sign or
     device is damaged it is to be replaced immediately.

     Record details of vandalism or tapering to signs and devices, noting actions taken with date and time

          10.2           TMP Audits and Inspections

     One compliance audit shall be conducted following setting up of the traffic management and prior to
     commencement of the works.

     Audit findings, recommendations and actions taken shall be documented and copies forwarded to the Project
     Manager and the Road Authority’s Representative

          10.3           Records

     A daily diary recording all inspections including variations to the approved TMP shall be kept using the Daily
     Diary.

     The Traffic Supervisor is to record all inspections and variations made on a daily basis and at those times
     prescribed by the Traffic Management Implementation Standards. Upon completion of each day the Traffic
     Supervisor shall provide copies of the daily diary record to the Project Manager.

          10.4           Public Feedback

     A register of all complaints shall be maintained and forwarded to the principal on a daily basis. AVADA Traffic
     shall be advised immediately of any incident or complaint involving the Public.




Document Set ID: 24005412
                  23806880Document MSF-AT-TMP-001| Issued 05 September 2024| Review: 05 September 2025| Owner: Trevor Leggett | Page: 41
Version: 1,
         0, Version Date: 06/08/2025
                          01/01/1900             [UNCONTROLLED IF WHEN PRINTED AFTER 05 September 2024]
Log in to download the original file

SUPERSEDED NEGOTIATED - OPW25 0042 - REFERENCE DOCUMENT (As Published).pdf · 18.6 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.