ACCESS AND PARKING

   The access for construction materials and equipment will be from Park
   Road via the existing driveway to No. 10 Park Road. The Builder is to
   submit written consent for the use of this access driveway and garage from
   the owner of No. 10 Park Road. Access for personnel will be via Allambi
   Rise and Park Road. Offsite parking will be required for most construction
   personnel.

   Most workers vehicles shall be parked in Allambi Rise or in the existing
   driveway and carport of 12 Park Road which is accessed by the 9A
   driveway Allambie Rise.

   All construction access is to be obtained from Allambi Rise via the existing
   easement subject to the following exceptions:

   a) A crane may be used for delivering prefabricated materials and the
       pier digging machine to the site.
   The use of the crane in Park Road is to occur on two (2) separate
   days only, first for the delivery of the pier digging machine and any
   prefabricated materials, the second to retrieve the pier digging
   machine and provide any further prefabricated materials as required.
   Traffic control is to be provided for the use of the crane in Park Road,
   in accordance with the builders Traffic Management Plan.

   b) Access from Park Road to the site is to be used for the purpose of
      a concrete pumping pipe to be located at the base of the rock
      retaining wall on the boundary of 10 Park Road, laid upon a
      composted wood chip mulch 600mm wide and 150mm thick. Any
      mulch contaminated by concrete or wastes shall be removed from
      the site. Any remaining clean mulch may be left in situ and spread
      to 50mm thickness.


MATERIALS HANDLING

   As previously described all prefabricated building materials will be
   delivered to site via Park Road. Manual material handling will be
   employed throughout the construction to minimize construction activities
   and impact on the site, especially existing vegetation.

   In addition a temporary builder’s hoist a temporary scaffold platforms
   will be erected in the existing driveway and within the property
   boundaries of 10 and 12 park road including a builders hoist over the
   existing Driveway to accommodate the mini concrete pump waste
   grout receptacles and to facilitate the easy removal of waste without
   using or traversing the road reserve.

   Temporary scaffold platforms and walkways will be constructed within the
   property boundaries in accordance with the Tree Protection Plan & AS
Log in to download the original file

Compiled Approved Plans - 132003.221152.8.pdf · 5.8 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.