AS PUBLISHED Negotiated Report (Representations made) MCU23 0094 · MCU23/0094
3. Prior to commencement of works within the development site, maintenance and rectification
of the underground stormwater drainage network downstream of the site is to be completed
and is to ensure that the capacity of the network is consistent with the capacity assumed in
the Stormwater Management Plan Rev C (prepared by SCG Consulting Engineers, dated
5.12.2023). SCG consulting engineers have reviewed the condition and seeks further
clarification regarding the wording. Council should not be able to condition the developer for
the maintenance & rectification of Council’s existing stormwater network prior to
commencement of works. If the existing network has been damaged it is prudent to advise
Council of the problem, however it is not the responsibility of the developer to rectify works
that could be hundreds of metres away from their site that they have not caused damage to.
Please review the wording of the condition.
Applicants Representation
SCG consulting engineers have reviewed the condition and seeks further clarification regarding
the wording. Council should not be able to condition the developer for the maintenance &
rectification of Council’s existing stormwater network prior to commencement of works. If the
existing network has been damaged it is prudent to advise Council of the problem, however it is
not the responsibility of the developer to rectify works that could be hundreds of metres away from
their site that they have not caused damage to. Please review the wording of the condition.
Assessment of Representation
Council’s Senior Development Engineer responds:
As no downstream capacity investigation had been undertaken as part of the Developer’s
stormwater design, the intent of the condition is to require confirmation that the capacity is
consistent with the SMP assumptions.
Council’s Development Engineer agrees with the deletion of Condition 3, and recommend that
Condition 8 be amended as follows:
8. A condition report of the drainage system must be completed for agreement at the prestart
meeting. The report is to confirm that the capacity of the network is consistent with the capacity
assumed in the Stormwater Management Plan Rev D (prepared by SCG Consulting Engineers,
dated 12/3/24). The report is to include a CCTV inspection of the existing pipe and must include at
least 50m upstream and downstream of all works.
PRELIMINARY APPROVAL FOR OPERATIONAL WORKS (OPW23/0113)
(Landscaping, Drainage Work, Stormwater)
Condition 1 of the Preliminary Approval for Operational Works
APPROVED PLANS
Condition 1
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
NIL - - -
The following plans require amendment.
Plan No. Rev. Plan/Document Name Date
33132-SW1.2 C Stormwater Details 5.12.2023
Page 11 of 25
Document Set ID: 22926712
Version: 8, Version Date: 13/05/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
AS PUBLISHED Negotiated Report (Representations made) MCU23 0094.pdfRelated documentApplication case desk ↗
About this file
- File size
- 932 KB (small file)
- File type
No other editions are linked here.