Skip to the record
Noosa’s premier civic archive.

Council archive · source document

AS PUBLISHED Negotiated Report (Representations made) MCU23 0094 · MCU23/0094

of 25

Text shows just the words. Original shows the document exactly as it was published.

               3.     Prior to commencement of works within the development site, maintenance and rectification
                      of the underground stormwater drainage network downstream of the site is to be completed
                      and is to ensure that the capacity of the network is consistent with the capacity assumed in
                      the Stormwater Management Plan Rev C (prepared by SCG Consulting Engineers, dated
                      5.12.2023). SCG consulting engineers have reviewed the condition and seeks further
                      clarification regarding the wording. Council should not be able to condition the developer for
                      the maintenance & rectification of Council’s existing stormwater network prior to
                      commencement of works. If the existing network has been damaged it is prudent to advise
                      Council of the problem, however it is not the responsibility of the developer to rectify works
                      that could be hundreds of metres away from their site that they have not caused damage to.
                      Please review the wording of the condition.
               Applicants Representation
               SCG consulting engineers have reviewed the condition and seeks further clarification regarding
               the wording. Council should not be able to condition the developer for the maintenance &
               rectification of Council’s existing stormwater network prior to commencement of works. If the
               existing network has been damaged it is prudent to advise Council of the problem, however it is
               not the responsibility of the developer to rectify works that could be hundreds of metres away from
               their site that they have not caused damage to. Please review the wording of the condition.

               Assessment of Representation
               Council’s Senior Development Engineer responds:
               As no downstream capacity investigation had been undertaken as part of the Developer’s
               stormwater design, the intent of the condition is to require confirmation that the capacity is
               consistent with the SMP assumptions.
               Council’s Development Engineer agrees with the deletion of Condition 3, and recommend that
               Condition 8 be amended as follows:
               8. A condition report of the drainage system must be completed for agreement at the prestart
               meeting. The report is to confirm that the capacity of the network is consistent with the capacity
               assumed in the Stormwater Management Plan Rev D (prepared by SCG Consulting Engineers,
               dated 12/3/24). The report is to include a CCTV inspection of the existing pipe and must include at
               least 50m upstream and downstream of all works.


                              PRELIMINARY APPROVAL FOR OPERATIONAL WORKS (OPW23/0113)
                                          (Landscaping, Drainage Work, Stormwater)
               Condition 1 of the Preliminary Approval for Operational Works
               APPROVED PLANS
               Condition 1
               1.     Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions.

                        Plan No.             Rev.    Plan/Document Name                            Date

                        NIL                  -       -                                             -

                      The following plans require amendment.

                        Plan No.             Rev.    Plan/Document Name                           Date

                        33132-SW1.2          C       Stormwater Details                           5.12.2023


                                                                                                       Page 11 of 25

Document Set ID: 22926712
Version: 8, Version Date: 13/05/2024

Used in these records

About this file

File size
932 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

AS PUBLISHED Negotiated Report (Representations made) MCU23 0094.pdf · 932 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.