Erosion and Sediment Control
57. A ‘for construction’ Erosion and Sediment Control Plan (E&SCP) must be provided to
Council’s Delegate at least 2 weeks prior to the on-site pre-start meeting and prior to works
commencing. The E&SCP must:
a. be prepared by a suitably qualified and experienced professional;
b. relate to each phase of the works (including clearing, earthworks, civil
construction, services installation and landscaping) and detail the type, location,
sequence and timing of measures and actions to effectively minimise erosion,
manage flows and capture sediment;
c. be consistent with current best practice standards to the extent that the standards
are not inconsistent with the conditions of approval and taking into account all
environmental constraints including erosion hazard, season, climate, soil, and
proximity to waterways;
d. provide sufficient detail regarding the manner in which compliance with all
conditions of this permit relating to E&SC is to be achieved;
e. include details of proposed flocculants and automatic dosing systems for sediment
basins, including jar testing results. Demonstrate the suitability of the proposed
flocculant having regard to the downstream receiving environment and water
quality; and
f. include the results of all soil investigations undertaken for the site and on which
the E&SCP is based
58. Prescribed Water Contaminants (as defined in the Environmental Protection Act 1994) must
not be released from the site or to waters within the site, or be likely to be released should
rainfall occur, unless all reasonable and practicable measures are taken to prevent or
minimise the release and concentration of contamination. These measures must be
designed, implemented and maintained in accordance with “Best Practice Erosion and
Sediment Control” published by the International Erosion Control Association (Australasian
Chapter) (IECA, 2008), to the extent that such measures and practices are also consistent
with the following:
(c) Minimise Erosion
(i) Restrict the extent of clearing to that necessary for access to and safe
construction of the approved works;
(ii) Protect vegetation in all other areas of the site;
(iii) Minimise the duration of soil exposure by undertaking land clearing and
stabilisation according to the rainfall erosion hazard as specified in IECA (2008)
Tables 4.4.2 and 4.4.7
(iv) Prior to either the approval of the plan of survey for the development or
commencement of use, all site surfaces are to be effectively stabilised using
methods that will continue to achieve effective stabilisation in the medium to long
term. For the purpose of this condition, an effectively stabilised surface is defined
as one that does not, or is not likely to result in visible evidence of soil loss caused
by sheet, rill or gully erosion or lead to sedimentation, or lead to water
contamination.
(d) Manage concentrated stormwater flows
(i) Implement drainage and erosion control measures (including contingency
measures), prior to rainfall, which prevent or minimise rill erosion and gully
erosion.
(ii) Ensure clean stormwater is diverted/managed around or through the site without
increasing the concentration of total suspended solids or other contaminants in
the flow and without causing erosion (on-site or off-site). If it is not feasible to
divert all areas discharging clean stormwater around or through the site, the clean
stormwater runoff is managed in the same manner as contaminated stormwater
Page 20 of 25
Document Set ID: 22926712
Version: 8, Version Date: 13/05/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
AS PUBLISHED Negotiated Report (Representations made) MCU23 0094.pdfRelated documentApplication case desk ↗
About this file
- File size
- 932 KB (small file)
- File type
No other editions are linked here.