GENERAL COMMITTEE MEETING AGENDA 18 OCTOBER 2021
Risks & Opportunities
Finance Risks Mitigation
Final contract value exceeds budget. Risk partly mitigated by an independent cost
estimate review undertaken at the completion of the
design.
Contingency using the budget estimate under the
Funding Agreement is at 24% or $1,214,315. Under
the Funding Agreement, overall project contingency
(an additional $1,582,630) is available if required
subject to TMR approval.
Time (program) risks Mitigation
Delays to Contract Award affecting the placement of Contract Award for SGQ Pty Ltd scope must be
earthworks requiring settlement of 2 months. executed in October 2021 in order to enable the
contractor to mobilise and complete earthworks
affected by settlement before the Christmas
shutdown period.
Contract documents are to be prepared and
transmitted to the Contractor as soon as tender
award is approved.
Council to ensure all required consultants including
Native Foresters (fauna management), Archeo
(cultural heritage) are aware of the program and are
planned to attend the site to achieve the Contractor’s
program.
Delays affecting the main civil contract. SGQ Pty Ltd can add additional resources if required
should the program require acceleration or mitigation
of delays.
Safety Risks Mitigation
SGQ Pty Ltd fails to ensure the work is conducted SGQ Pty Ltd will be appointed as the Principal
safely and in accordance with minimum standards. Contractor responsible for workplace health & safety
for the site.
Prior to commencement of construction, SGQ Pty
Ltd management plans, Safe Work Method
Statements, Job Hazard Analysis (or similar) and
other documentation will be submitted, reviewed,
and accepted by Council.
Council will undertake surveillance, regular safety
audits and inspections throughout the construction
period.
Scope & Quality Risk Mitigation
The Contractor fails to construct the scope of work SGQ Pty Ltd is highly skilled with constructing civil
to the minimum standard. and roadworks with extensive experience working
with Council’s and TMR, and the nominated
specifications for this project.
The quality of workmanship in the field will be
monitored with regular Council surveillance with
availability of technical support from the engineering
consultant if required.
Page 10 of 67
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.