GENERAL COMMITTEE MEETING AGENDA 18 OCTOBER 2021
Resource Risk Mitigation
Scope, quality, safety, and program are affected due SGQ Pty Ltd have nominated a highly capable team
to resource shortages. for this project and can add additional and
appropriately skilled resources as required.
Council have added an external resource (Capital
Works Consultant) who has been procured as a
dedicated resource to provide project management,
surveillance, and contract administration support.
Council can engage the designer responsible for the
design and additional engineering consultants as
required to attend inspections if required.
Council can utilise internal resources to attend
inspections or assist with documentation if required.
Consultation
External Consultation - Community & Stakeholder
Roadpro have been engaged to provide community and stakeholder communication support. The
proposed communication program for the main civil works builds on the stakeholder engagement
and proactive communication undertaken during design and early works phases, with consistency
in key messaging, existing general community awareness about the upcoming works, and
communication methods that reflect a greater understanding of impacted stakeholders.
Communication material includes project newsletters, Facebook posts and stakeholder emails.
To coincide with the start of major construction, a sod-turning event with the Minister for Transport
and TMR is tentatively scheduled for the week starting 9 November 2021. This event will be held on
site and provide an opportunity to promote the project and the benefits for the Noosa Shire.
Separate consultation has been made with TMR (party to the Funding Agreement) regarding this
tender, program, and budget.
Internal Consultation
Corporate Services (Procurement)
Infrastructure Services (Infrastructure Planning, Design and Delivery)
Departments/Sections Consulted:
Chief Executive Officer Community Services X Corporate Services
Executive Support Director Director
Community Development Financial Services
Community Facilities Fleet
Libraries & Galleries ICT
Local Laws X Procurement
Waste & Environmental Health Property
Revenue Services
Executive Services Environment & Sustainable Development X Infrastructure Services
Director Director Director
Community Engagement Building & Plumbing Services Asset Management
Customer Service Development Assessment Buildings and Facilities
Governance Economic Development Civil Operations
People and Culture Environmental Services Disaster Management
Strategic Land Use Planning X Infrastructure Planning,
Design and Delivery
Page 11 of 67
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.