4 SPP 1/03 Compliance Assessment
SPP 1/03 sets out the specific outcomes that should be achieved for development to be compatible with the
nature of the natural hazard as required under Outcome 1 of the SPP which states that:
Within natural hazard management areas, development to which this SPP applies is
compatible with the nature of the natural hazard, except where:
> the development proposal is a development commitment; or
> there is an overriding need for the development in the public interest, and no other site
is suitable and reasonably available for the proposal.
SPP 1/03 defines a bushfire natural hazard management area as:
> land that has been identified as having either a Medium or High hazard rating; and
> a safety buffer that encompasses land within 100m of an area with a High bushfire hazard rating (or 50m
from an area with a Medium bushfire hazard rating) in recognition of the affect bushfires can have on
adjacent land due to winds fanning flames, smoke, embers and radiant heat.
For the purpose of this assessment reference is made to the development layout presented in the Noosa on
Weyba Concept Master Plan (refer Appendix A) which illustrates a potential development layout that would
be consistent with the Preliminary Approval being sought for the Noosa on Weyba project. The ultimate
layout and form of any development that is permitted will be the subject of further detailed planning and
assessments carried out in accordance with the conditions of any Preliminary Approval that is issued by
Council for the Noosa on Weyba project.
With respect to the above, it is noted that parts of the proposed Noosa on Weyba urban development
precincts will be located within a Medium Bushfire Hazard Management Area that encompasses a 50m wide
“safety buffer” surrounding areas classified as having a Medium bushfire hazard classification. The location
of areas classified as having a composite Medium bushfire hazard classification is illustrated in Figure 4,
along with other bushfire hazard mitigation measures upon which the Noosa on Weyba proposal would
depend.
The Concept Master Plan must be consistent with the objectives of SPP 1/03 as they relate to maintaining
the safety of people and property, by:
a) avoiding areas of High or Medium bushfire hazard; or
b) mitigating the risk through:
i. allotment design and the siting of buildings; and
ii. including firebreaks that provide adequate:
setbacks between buildings/structures and hazardous vegetation, and
access for fire-fighting/other emergency vehicles;
iii. providing adequate road access for fire-fighting/other emergency vehicles and safe
evacuation; and
iv. providing an adequate and accessible water supply for fire fighting purposes.
The Concept Master Plan will largely achieve compliance with objective a) of SPP 1/03 (i.e. locating
development on land that is not subject to a High or Medium bushfire hazard), except in those areas where
residential lots are proposed within the 50m wide bushfire safety buffer to areas that have a Medium bushfire
hazard rating. Any future urban development in these areas must satisfy the intent of objective b) to achieve
compliance with SPP 1/03 as it relates to maintaining the safety of people and property. An assessment of
compliance with the requirements of objective b) is provided in Sections 4.1 to 4.5 below.
Northbrook Corporation Pty Ltd Version 2 11 October 2013
Bushfire Assessment Report v2.docx Commercial in Confidence Page 10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 9- Amended Bushfire Assessment Report MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 11.7 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.