Council archive · source document
Attachment 9- Amended Bushfire Assessment Report MCU12/0208
Very large file (11.7 MB): the original may take a few minutes to open or download. The page text below is quick to read.
Noosa on Weyba
Bushfire Assessment Report
2 Proposed Plan of Development
The proposed Noosa on Weyba Precinct Plan is presented in Appendix A. For the purpose of this
assessment and as part of the Noosa on Weyba design process a Concept Master Plan was also prepared
to examine in greater detail a potential form of urban development that could occur if the current MCU
Application was to be approved. The Noosa on Weyba Concept Master Plan is also presented in Appendix
A.
The proposed Noosa on Weyba Master Plan will result in 19% of the total area being dedicated to urban
development with the remaining 81% being retained for parkland and conservation purposes. Over 45% of
the Noosa on Weyba site will be dedicated to the State for incorporation into the Noosa National Park in
accordance with the Noosa on Weyba Biodiversity Development Offset Area (BDOA) declaration.
The proposed urban portion of the Noosa on Weyba site will accommodate approximately 876 dwellings in a
mixed density configuration as well as access roadways and associated infrastructure. It is proposed that
future allotments would be established into approximately three sub-categories with different densities as
follows:
> 493 residential lots at an average density of approximately 13 lots per ha;
> 377 medium density dwellings comprising apartment, townhouse and retirement living at an average of
approximately 26 lots per ha; and
> 6 rural and special residential lots at an average of approximately 5 lots per ha.
Key aspects of the proposed plan of development for the Noosa on Weyba project from a bushfire hazard
assessment perspective are as follows.
1. Dedication of approximately 140 hectares of high conservation value land located in the north-eastern
sectors of the site to the State for incorporation into the Noosa National Park estate, including
implementation of revegetation works within approximately 8.4 hectares of land that have previously
been cleared.
2. Retention of approximately 92 hectares of high conservation value land, located within that part of the
Noosa on Weyba project site that is to be retained in private ownership, which is to be managed for
conservation purposes.
3. Management of retained areas of high conservation value land, in collaboration with adjoining land
owners, Council, Qld National Parks and Wildlife Service (QPWS) and the Qld Fire and Rescue
Service (QFRS), to facilitate:
- the implementation of a planned fire (prescribed burn) regime, approximating natural fire regimes,
to meet the requirements of the native plants and animals; and
- the avoidance of unplanned fires (wildfires) that may threaten the biodiversity values of the
reserved land and human health and property located on adjacent land.
4. Establishment of residential land uses within 58 hectares (or approximately 19%) of the Noosa on
Weyba site, which areas have been selectively cleared and do not support areas of remnant
vegetation or koala bushland habitat.
5. Maintenance of appropriate building setbacks, generally in the order of 30m, between residential land
uses and adjacent areas of potentially hazardous bushland vegetation located within or external to the
Noosa on Weyba site.
6. Establishment of new road infrastructure and upgrading of existing road infrastructure, to:
- service the proposed Noosa on Weyba project, in a manner that is designed to cater for the
deployment of fire response vehicles and if required the safe evacuation of residents and visitors
in the event of a significant bushfire threat; and
Northbrook Corporation Pty Ltd Version 2 11 October 2013
Bushfire Assessment Report v2.docx Commercial in Confidence Page 2
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 9- Amended Bushfire Assessment Report MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 11.7 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.