SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 11 MAY 2021
3. Works in Progress
Design and delivery activities have further increased during the third quarter with a number of
projects reaching milestones. These include:
Hinterland Playground - Site fencing was established in early April, site excavations are
currently in progress (Image 4 below). Design development to suit flood modelling levels and
final arrangements are ongoing. Contract is on track to finish by December 2021
Rufous Street – Construction has commenced on the Community House with pad footings
being excavated, sheet piling and installation of underground water tanks. Design of the Digital
Hub has also commenced. See Images 5 & 6.
Hilton Terrace (Ivory Palms) Footpath, Tewantin – Works in progress with completion expected
by early May.
Sunrise Beach Sobraon Street Slope Stabilisation – Design being finalised (currently at 70%),
early site investigation works are underway with construction on track to commence early June
Expected project completion is September 2021.
Peregian Beach Boardwalk – At tender approval process. Starting on site in early May, for
completion by the end of financial year.
Project Avenue Stormwater, Noosaville – Design will be finalised in April with the tender to be
advertised in May.
Eenie Creek Roundabout – Bridge abutment remediation works programmed for early May.
This is the first component in a series of road safety improvements including kerb realignment
and resealing the roundabouts road surface.
Hinterland Bridges (Cooroy Belli Creek Road Bridge & Lawnville Road Bridge) – the Projects
team are currently in the process of evaluating tender responses received.
Image 4: Hinterland Playground - Excavation of Western Remediation Area
Page 28 of 96
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.