Negotiated Report (Representations made) MCU26 0064 & OPW26 0093 (As Published) · MCU26/0064

of 5

Text shows just the words. Original shows the document exactly as it was published.

               REQUEST FOR NEGOTIATED DECISION REPORT
               Author
                                       Murray Nagle, Development Engineer



                  APPLICATION DETAILS

                  Application No.                     MCU26/0064 OPW26/0093

                  Development Approval                Material Change of Use - Landing – Residential
                                                      Operational Works – Jetty

                  Applicant                           Andrew Peter Grant
                                                      Tegan Briellen Grant

                  Representations Received On         25 September 2026

                  Negotiated Decision Due Date        12 October 2026

                  Report Reviewed & Finalised         Daniel Epps – 12 October 2026
                  By

                  Number of Submissions for           NIL
                  Original Application


                  PROPERTY DETAILS

                  Property Address                    18 Masthead Qy Noosaville Qld 4566

                  RP Description                      Lot 625 RP 883863

                  Land Area                            874.0000 m²

                  Existing Use of Land                Residential


                  STATUTORY DETAILS

                  SEQRP Designation                   Urban Footprint

                  Zone                                Low Density Residential

                  Precinct                            Not applicable

                  Local Area Plan                     Noosaville

                  Overlays                            Land Subject to Acid Sulphate, Flooding and Inundation
                                                      Extent, Landslide Hazard.

                  Assessment Type                     Representations made to original approval



                                                                                                       Page 1 of 5

Document Set ID: 25242703
Version: 3, Version Date: 12/10/2026
Full text of the other 4 pages

Page 2

               1.     BACKGROUND
               A Development Permit for a Material Change of Use - Landing - Residential and Operational Works
               – Jetty was issued on 10 September 2026
               The applicant suspended the appeal period and made representations on 25 September 2026 to
               the development approval conditions. The representations are detailed below but primarily relate
               to re-engineering of the proposed jetty approved on the 10th of September 2026 to substitute timber
               construction with alternative materials including concrete insitu piles, aluminium framing and
               composite decking to improve durability, longevity and reduce maintenance requirements of the
               completed jetty.
               The requested doesn’t comply with Acceptable Outcome 19.1(c) of the Waterways Works Code
               by not being constructed with timber. The proposal does satisfy the corresponding Performance
               Outcome for the reasons discussed above.
               The updated plans submitted with the representation also indicate an increased jetty head length
               of 200mm that does not result in an exceedance of the permitted jetty head area or contravention
               of offsets to the prolongation of boundaries. As such the proposed jetty remains compliant.
               2.     ASSESSMENT
               An assessment in relation to each of the submitted representations is provided below:
               Existing Condition 1
               APPROVED PLANS
               1.     Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions.

                         Plan No.          Rev.    Plan/Document Name                            Date

                         S01               C1      Drawing Schedule & Transmittal                29/06/2026
                                                   Prepared by      Long    View    Consulting
                                                   Engineers

                         S02               C1      Structural notes Sheet                        29/06/2026
                                                   Prepared by      Long    View    Consulting
                                                   Engineers

                         S03               C1      Site Plan, Framing Plan, Elevations           29/06/2026
                                                   Prepared by Long View Consulting
                                                   Engineers

                         S04               C1      Jetty Framing Details Sheet 1                 29/06/2026
                                                   Prepared by Long View Consulting
                                                   Engineers

                         S05               C1      Jetty Framing Details Sheet 2                 29/06/2026
                                                   Prepared by Long View Consulting
                                                   Engineers


               Applicant’s Request
               The applicant has requested existing condition ‘1’ be amended and replaced with the following
               amended condition:


                                                                                                     Page 2 of 5

Document Set ID: 25242703
Version: 3, Version Date: 12/10/2026

Page 3

               APPROVED PLANS
               1.     Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions.

                         Plan No.          Rev.    Plan/Document Name                             Date

                         -                 A       COVER SHEET                                    25/08/2026
                                                   Prepared by KUNKEL BUILDING DESIGN

                         SHEET NO 01       A       SITE PLAN                                      25/08/2026
                                                   Prepared by KUNKEL BUILDING DESIGN

                         SHEET NO 02       A       FLOOR PLAN, FLOOR FRAMING PLAN &               25/08/2026
                                                   TYPICAL SECTION
                                                   Prepared by KUNKEL BUILDING DESIGN

                         -                 A       DRAWING REGISTER                               01/09/2026
                                                   Prepared by HR DESIGN CONSULTING
                                                   ENGINEERS

                         Job No.:26-0512   A       GENERAL NOTES                                  01/09/2026
                         SO1                       Prepared by HR DESIGN CONSULTING
                                                   ENGINEERS

                         Job No.:26-0512   A       FOOTING LAYOUT & DETAILS                       01/09/2026
                         SO2                       Prepared by HR DESIGN CONSULTING
                                                   ENGINEERS

                         Job No.:26-0512   A       BEARER & JOISTS LAYOUT (Deck)                  01/09/2026
                         SO3                       Prepared by HR DESIGN CONSULTING
                                                   ENGINEERS

                         Job No.:26-0512   A       CONNECTION DETAILS                             01/09/2026
                         SO4                       Prepared by HR DESIGN CONSULTING
                                                   ENGINEERS

               Assessment of Request
               The request to change the condition is considered reasonable to reflect the latest jetty design.
               Recommendation
               It is recommended existing condition ’1’ be amended to read as follows:
               APPROVED PLANS
               1.     Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions.

                         Plan No.          Rev.    Plan/Document Name                             Date

                         S01               C1      Drawing Schedule & Transmittal                 29/06/2026


                                                                                                      Page 3 of 5

Document Set ID: 25242703
Version: 3, Version Date: 12/10/2026

Page 4

                                                Prepared by      Long    View   Consulting
                                                Engineers

                         S02               C1   Structural notes Sheet                       29/06/2026
                                                Prepared by Long View Consulting
                                                Engineers

                         S03               C1   Site Plan, Framing Plan, Elevations          29/06/2026
                                                Prepared by Long View Consulting
                                                Engineers

                         S04               C1   Jetty Framing Details Sheet 1                29/06/2026
                                                Prepared by Long View Consulting
                                                Engineers

                         S05               C1   Jetty Framing Details Sheet 2                29/06/2026
                                                Prepared by Long View Consulting
                                                Engineers

                         -                 A    COVER SHEET                                  25/08/2026
                                                Prepared by KUNKEL BUILDING
                                                DESIGN

                         SHEET NO 01       A    SITE PLAN                                    25/08/2026
                                                Prepared by KUNKEL BUILDING
                                                DESIGN

                         SHEET NO 02       A    FLOOR PLAN, FLOOR FRAMING PLAN               25/08/2026
                                                & TYPICAL SECTION
                                                Prepared by KUNKEL BUILDING
                                                DESIGN

                         -                 A    DRAWING REGISTER                             01/09/2026
                                                Prepared by HR DESIGN CONSULTING
                                                ENGINEERS

                         Job No.:26-0512   A    GENERAL NOTES                                01/09/2026
                         SO1                    Prepared by HR DESIGN CONSULTING
                                                ENGINEERS

                         Job No.:26-0512   A    FOOTING LAYOUT & DETAILS                     01/09/2026
                         SO2                    Prepared by HR DESIGN CONSULTING
                                                ENGINEERS

                         Job No.:26-0512   A    BEARER & JOISTS LAYOUT (Deck)                01/09/2026
                         SO3                    Prepared by HR DESIGN CONSULTING
                                                ENGINEERS

                         Job No.:26-0512   A    CONNECTION DETAILS                           01/09/2026
                         SO4                    Prepared by HR DESIGN CONSULTING
                                                ENGINEERS


                                                                                                Page 4 of 5

Document Set ID: 25242703
Version: 3, Version Date: 12/10/2026

Page 5

               3.     CONCLUSION & REASONS FOR DECISION
               The proposed development generally complies with the requirements of the planning scheme. The
               requested changes to the conditions do not raise any significant issues and are therefore
               supported. The application is therefore recommended for approval.
               The report is provided in accordance with Section 76 of the Planning Act 2016.
               RECOMMENDATION
               With regard to Application No. MCU26/0064 OPW26/0093, and the representations made, Council
               on 12 October 2026 decided to:
               A.     Agree to amend conditions 1 to read as follows:
               APPROVED PLANS
               1.     Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions.

                         Plan No.           Rev.   Plan/Document Name                            Date

                         -                  A      COVER SHEET                                   25/08/2026
                                                   Prepared by KUNKEL BUILDING DESIGN

                         SHEET NO 01        A      SITE PLAN                                     25/08/2026
                                                   Prepared by KUNKEL BUILDING DESIGN

                         SHEET NO 02        A      FLOOR PLAN, FLOOR FRAMING PLAN &              25/08/2026
                                                   TYPICAL SECTION
                                                   Prepared by KUNKEL BUILDING DESIGN

                         -                  A      DRAWING REGISTER                              01/09/2026
                                                   Prepared by HR DESIGN CONSULTING
                                                   ENGINEERS

                         Job No.:26-0512    A      GENERAL NOTES                                 01/09/2026
                         SO1                       Prepared by HR DESIGN CONSULTING
                                                   ENGINEERS

                         Job No.:26-0512    A      FOOTING LAYOUT & DETAILS                      01/09/2026
                         SO2                       Prepared by HR DESIGN CONSULTING
                                                   ENGINEERS

                         Job No.:26-0512    A      BEARER & JOISTS LAYOUT (Deck)                 01/09/2026
                         SO3                       Prepared by HR DESIGN CONSULTING
                                                   ENGINEERS

                         Job No.:26-0512    A      CONNECTION DETAILS                            01/09/2026
                         SO4                       Prepared by HR DESIGN CONSULTING
                                                   ENGINEERS



                                                                                                    Page 5 of 5

Document Set ID: 25242703
Version: 3, Version Date: 12/10/2026

Used in these records

About this file

File size
126 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Negotiated Report (Representations made) MCU26 0064 & OPW26 0093 (As Published).pdf · 126 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.