NOOSA COUNCIL IDAS Development Application Decision Notice 11 of 24
87. Boundary wall movement shall be monitored throughout construction and if movement occurs -
construction is to be stopped immediately and appropriate action is to be taken to arrest the movement.
Further work shall only take place after a re-assessment of the conditions on site by the Geotechnical
engineer and Noosa Council’s Manager of Building Services.
88. Earthworks carried out on site shall not affect the structural integrity of any of the existing fences or
structures that border the development site. In this regard any fences to be replaced shall be clearly
shown on the plans submitted for Operational Works approval. Fences that are affected shall be replaced
prior to the Building Certifier issuing the Certificate of Classification.
89. The builder, landscaper and all workers associated with the construction of the proposed development
shall at all times comply with the directions of the Geotechnical engineer and the reasonable and lawful
directions of Council officers.
90. Any filling works required on site shall be carried out in accordance with Section 3.8 of Council’s
Engineering Design Standards Manual and so as not to cause the ponding of water on any adjoining
lands or the blockage of, or interference with, any natural watercourses. Detailed site surveys indicating
natural surface levels and contours of the adjoining properties must be provided with the application for a
Development Permit for Operational Works for Filling and Drainage.
91. A Registered Professional Engineer Queensland shall certify all designs and certify that he or she has
supervised all engineering works and that all works have been completed in a workmanlike manner in
accordance with the Australian Standards and good engineering practice.
Construction Issues
92. A Construction Management Plan (including a Traffic Management Plan) addressing all construction
phases shall be prepared by suitably qualified persons in consultation with the Peregian Beach Business
Association and submitted to Council for approval prior to obtaining a Development Permit for Operational
Works. The report should aim to address every foreseeable problem that is likely to occur during the
construction process and include recommendation on how these can be overcome or minimised and shall
also address parking for construction workers.
To ensure construction is undertaken appropriately, the Construction Management Plan shall also include
a section written by a Geotechnical engineer addressing the excavation and surrounding site support
systems.
93. A Condition Survey is to be carried out on adjoining buildings, structures and services prior to any
excavation or construction works taking place on site. If distress already exists, a photographic survey
shall be undertaken, the distress measured and a plan to monitor changes to distress shall be
implemented. A copy of this report is to be submitted to Council within 5 business days of the survey and
prior to construction work proceeding.
This report will be held by Council until all work is completed and will be used for verification purpose and
to ensure that all buildings, structures and services are left in at least the same state as before
construction commenced.
94. The use of vibratory equipment of any kind is not permitted to be used (including vibrating rollers and the
use of vibrating installation techniques for sheet piling and other construction vibrations caused by
excavating, earthmoving or demolition machinery or other similar construction techniques) unless
approved and supervised by a Certified Geotechnical Engineer. Under such circumstances the operator
of such equipment shall at all times comply with the directions of the Geotehcnical engineer and the
reasonable and lawful directions of Council officers.
The proposed use of such equipment shall be detailed in any application for a Development Permit for
Operational Works.
Erosion and Sediment Control
95. Any person acting on this permit shall prevent erosion and sediment export from leaving the site. Site
control measures such as silt fencing, controlled gravel access to the site and controlled disposal of
waste, will be necessary.
In this regard plans detailing the methods of controlling erosion and sediment are required to be submitted
to the Council for approval prior to obtaining a Development Permit for Operational Works.
General
96. A suitably qualified Registered Professional Engineer shall prepare engineering drawings and
specifications for all engineering works that will become Council infrastructure, which shall be submitted in
conjunction with an application for a Development Permit for Operational Works. In this regard a
DXF/DWG file on GDA94 zone 56 grid of the proposed cadastre layout is to be submitted in conjunction
with any application for Operational Works.
A c:\docume~1\tblogg\locals~1\temp\bcl technologies\easypdf 5\@bcl@6c06e85a\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
05/1917 - SUPERSEDED Compiled Decision Notice [As Published]Related documentApplication case desk ↗
05/1917 - SUPERSEDED Compiled Decision Notice [As Published]Related documentApplication case desk ↗
05/1917 - SUPERSEDED Compiled Decision Notice [As Published]Related documentApplication case desk ↗
About this file
- File size
- 339 KB (small file)
- File type
No other editions are linked here.