Stormwater Drainage
69. All stormwater drainage shall be collected on site and discharged so there is no net increase in
stormwater runoff from the site. Stormwater drainage permitted to drain from the site shall be discharged
to Council’s existing drainage structures in Kingfisher Drive. Plans of the drainage design shall be
prepared by a Registered Professional Civil Engineer and submitted to Council prior to obtaining a
Development Permit for Operational Works. In this regard the capacity of Council’s existing drainage
system shall be determined in order to ensure that the existing system has capacity to carry additional
flows.
70. Roof runoff from any new buildings shall be directed to a rainwater storage system or tank (with a
2
minimum storage capacity of 12 litres/m of roof area) that is installed to ensure water from the tank can
be used for external uses (such as watering gardens, irrigation, ornamental ponds, water features,
topping-up swimming pools, outdoor cleaning, etc) and for use in flushing of toilets internal to the building.
All rainwater tanks are to be designed and installed in accordance with the Queensland Development
Code (QDC), Part 25 – Rainwater Tanks, and to the satisfaction of Council’s Manager Plumbing Services.
The location and capacity of the tanks shall be clearly shown on the plans submitted for Building Works
approval and any overflow shall be directed to the stormwater drainage system for the development.
71. All stormwater on site, except roof water, shall be discharged through an approved Gross Pollutant Traps
(GPT) prior to being permitted to discharge into Council’s drainage system.
To this end, a detailed maintenance plan shall be prepared for the GPT, which shall be submitted to the
Council for approval prior to obtaining a Development Permit for Operational Works.
The approved maintenance plan shall be incorporated in the Community Management Scheme for the
development (if no Community Management Scheme then in the development’s maintenance plans) and
a copy of this shall be provided for Council’s records prior to commencement of the approved Use.
72. Any GPT proposed within the basement carpark shall be capable of being serviced and maintained by
ensuring sufficient head clearance over the GPT.
73. All site stormwater drainage shall be by means of a gravity system in accordance with section 3.4.4.12 of
Council’s Planning Scheme.
74. All stormwater drainage lines that will become a Council asset shall be inspected by closed circuit
television (CCTV) prior to commencement of the approved Use.
CCTV inspection will be carried out by Council's CCTV contractor and arranged by Council following
satisfactory completion of construction works. The developer will be responsible for the full cost of CCTV
inspection, including any additional inspection necessary following defect identification and rectification.
This charge is payable prior to the issue of Operational Works approval and will be determined on the unit
rate basis current at the time of approval.
75. Plans of the drainage scheme shall be prepared by a Registered Professional Civil Engineer and
submitted to Council prior to obtaining a Development Permit for Operational Works. The applicant shall
note that a Development Permit for Building Works will not be granted until a Development Permit for
Operational Works has been issued in regard to the drainage scheme.
Sewer Mains
76. The site shall be connected to Council’s existing sewerage reticulation systems and be constructed in
accordance with Council’s standards and requirements at no cost to Council.
77. The existing sewer main that currently crosses part of the site shall be relocated at no cost to Council to
make way for the new development and basement car park.
78. All existing and/or future sewer mains within the site or adjacent to the site which are intended to remain,
shall be accurately located by a licensed Surveyor whom shall determine their ‘zone of influence’ (taken
as the area within a 45-degree angle measured from the invert of the sewer main to the finished surface
level) and arrange for easements to be created over these mains where the ‘zone of influence’ impacts on
the subject site.
This ‘zone of influence’ for both existing sewer mains and proposed sewer mains shall be shown on all
plans submitted for Operational Works approval and Building Works approval to ensure no damage
occurs and no encroachments result.
79. To ensure Council’s sewer mains are accessible for maintenance purposes and are protected from risk of
damage, no structures requiring a building permit (eg. buildings, swimming pools, retaining walls
exceeding 1m in height, raised terraces, etc) shall be constructed within this ‘zone of influence’ and as
such the applicant shall amend Operational Works plans, including Building plans to ensure compliance.
A c:\docume~1\tblogg\locals~1\temp\bcl technologies\easypdf 5\@bcl@6c06e85a\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
05/1917 - SUPERSEDED Compiled Decision Notice [As Published]Related documentApplication case desk ↗
05/1917 - SUPERSEDED Compiled Decision Notice [As Published]Related documentApplication case desk ↗
05/1917 - SUPERSEDED Compiled Decision Notice [As Published]Related documentApplication case desk ↗
About this file
- File size
- 339 KB (small file)
- File type
No other editions are linked here.