MCU14/006 - Response to Information Request · MCU14/0006
Our response:
The site can be developed with the available and common technology for excavation, sheet
piling, retaining walls etc, ensuring that there is no threat to neighbouring buildings. The
earth excavation will be done with great caution; adjoining buildings are over 4 m away from
the excavation area. We are aware of the need to ensure careful excavation and will
supervise the contractor accordingly.
We agreed that there is no need to provide a geotechnical investigation for the proposed
development at this stage. These technical aspects will be dealt with later (which is, we
believe, the belter time for it to be detailed) and the additional information will be provided
before construction commences.
The most appropriate solution for excavation will need to be discussed in detail with the
commissioned contractor once the detailed planning is more advanced; however, this does
not affect the ability to assess the submilted development application at this time.
We can confirm that a report will be prepared by a suitably qualified person and will include
recommendations to address any potential risks to the adjoining properties.
In addition, we can confirm that the drawings of SCG Engineers for DRIVEWAY and WATER
MANAGEMENT are part of the application and that their recommendations will be adhered
to in the project.
We hope this clarifies all additional information requested, and look forward to hear from
again.
Yours faithfully,
!~-
Steffen Lehmann and Apare da D. de \6.ragao-Lehmann
3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
MCU14/006 - Response to Information RequestRelated documentApplication case desk ↗
About this file
- File size
- 1.4 MB (small file)
- File type
No other editions are linked here.