OPERATIONAL PLAN 2024-25 Q3 QUARTERLY REPORTING (Referred from Services and Organisation Committee Meeting dated 10 June 2025 - Item 8.1) · Attachment 1 - Q3 Operational Plan Update
Plans and drawings: the text below has words only, no drawings.
Initiatives on Target
OP Ref Initiative Service/Mgr Responsible Status Reason for Status
2.3.2 Prepare for the delivery of the biennale Floating Arts and Culture Manager On Track Preparations for Floating Land 2025 'Escape Making' are well
Land 2025 event which brings arts and culture to a underway with the completion of the first artist camp at Boreen
contemporary community. Point and the opening of applications for contributions. The
event will run from 28 June to 27 July, 2025.
2.4.1 Complete and deliver the Movement and Strategy and Sustainability On Track Review of actions included in the Transport Plan and Cycling and
Connection Delivery Plan to improve transport Manager Walking Strategy undertaken. A draft Delivery Plan prepared for
links, walking and cycling connections and internal review. Draft to be discussed at Councillor workshop
movements. April 2025.
2.4.2 Commence a Northern Sunshine Coast Public Infrastructure Planning On Track The NSCPTS is progressing as scheduled, with Noosa Council
Transport Strategy including advocating with Design & Delivery actively working in partnership with TMR, Sunshine Coast
DTMR for the finalisation of the strategy and Manager Council and consultants to advance the draft plan. A draft plan
undertaking investigations into the Cooroy and is anticipated to be released in coming months for broader
Shire transit hubs to improve public transport review.
connectivity in the shire for residents and visitors.
2.4.3 Deliver the Cycling and Walking Implementation Infrastructure Planning On Track Pathways works are being delivered across the Shire as part of
Plan to guide Council’s planning, development and Design & Delivery the 24/25FY Capital Works program. The Implementation plan
promotion of bike and walking networks in the Manager is being used to support project bids and grant submissions for
future. the 25/26FY capital works program. Key initiatives that have
progressed include the Noosa Coastal Pathway (Peregian Beach
Active Street), Noosa Drive Pathway Design, Noosa Parade
Stage 2 Design, grant submissions for Hilton Esplanade Cycle
Street and Pomona Walking Network Plan and the delivery of
the Local Links footpath program including the connector to
Pomona Secondary College.
2.4.4 Develop the Noosa Parking Management Plan to Infrastructure Planning On Track The Parking Management Plan is progressing well. The draft
guide our approach to the management of parking Design & Delivery framework and local area plans have been prepared and subject
throughout the shire. Manager to a series of Councillor workshops to review and refine content
before broader community engagement later this year.