Details of Initiatives that are experiencing delays/disruptions:
Initiatives not on Target
OP Ref Initiative Service/Mgr Responsible Status Reason for Status
2.2.2 Finalise the Noosa Botanic Gardens Master Plan to Civil & Asset Operations Minor Stakeholder Reference Group and Internal Working Groups
Disruption
help guide future improvements and enhance the Manager meetings were conducted late 2024 including presentation of
visitor experience. initial concepts for feedback. Initial public consultation
undertaken. Consultants have advanced draft plan. Further
stakeholder reference group meetings held in March 2025
which has led to further plan refinement. Draft plan proposed
to submitted for Council in July 2025 for endorsement for
further public consultation.
2.5.5 Finalise the review of community purpose land and Property Manager Minor A second councillor workshop was undertaken. Councillors have
Disruption
the Infrastructure Tenure Policy to provide a requested for external stakeholder consultation occur. It was
consistent framework to ensure the equitable use agreed that this will likely extend timing into next financial year
of community purpose land and infrastructure in terms of the completion of the review and adoption of an
within is utilised to its full potential. updated policy.
2.6.1 Undertake the preparatory phase for the proposed Community Connection Major No internal staffing or funding for external resourcing available
Disruption
development of a new Community Strategy which Manager to begin this initiative this quarter and this is unlikely to change
outlines the community’s vision for Noosa and for the remainder of the financial year. Budget request
guides planning and decision making. submitted.
2.7.1 Complete Noosa Cemeteries Plan to guide the Community Connection Minor Consultation has been undertaken with key stakeholders. Draft
Disruption
future management of council’s cemeteries and Manager has been completed and under review. Progress constrained by
ensure cemetery services meet future demand. available resourcing.
2.7.4 Continue to progress asset management planning Community Services Minor Building condition assessment reports (BCARs) 40% completed
Disruption
for council’s community services buildings and Director with further BCARs underway. 28% of comprehensive Asset
community infrastructure to ensure their ongoing Management Plans (AMPs) near completion. Progress
suitability to meet the functional needs of current constrained by available resourcing. Budget request submitted.
and future users.