OPERATIONAL PLAN 2024-25 Q3 QUARTERLY REPORTING (Referred from Services and Organisation Committee Meeting dated 10 June 2025 - Item 8.1) · Attachment 1 - Q3 Operational Plan Update

of 29

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
                  18
                  16
                  14
                  12
                  10
                   8
                   6
                   4
                   2
                   0
                             Environment             Liveability              Prosperity                   Future          Excellence

                                                      Complete     On Track   Minor Disruption   Major Disruption




Comments:
The 2024–25 Operational Plan is both ambitious and comprehensive, incorporating numerous strategic initiatives aimed at advancing Council’s Corporate
Plan goals. However, several factors have affected the timely delivery of certain projects:
   •   Extended Consultation Periods:
       Elevated levels of community interest and participation—particularly in relation to the Noosaville Foreshore Infrastructure Management Plan—have
       resulted in longer-than-anticipated engagement processes. This has had a flow-on effect, delaying other initiatives such as the Destination
       Management Plan and the Noosa River Catchment Management Plan.
   •   Resource Limitations:
       Ongoing resourcing challenges continue to impact the delivery of key programs. Notable examples include delays in the implementation of the Eastern
       Beaches Management Plan and constraints affecting elements of the Capital Works Program. These challenges are not uncommon in local
       government, where finite staffing and budgetary resources must be balanced against an increasingly broad scope of responsibilities, rising community
       expectations, and emerging priorities. As such, trade-offs are often required, and project timelines may be adjusted to reflect available capacity.
   •   Emerging Priorities and External Events:
       The reprioritisation of resources to respond to unforeseen events has also influenced progress. During the reporting period, Council was required to
       divert resources to support preparations for ex-Tropical Cyclone Alfred and respond to significant rainfall events in March 2025. These emergent
       demands have temporarily shifted focus away from planned initiatives, placing additional pressure on operational capacity, particularly on the Capital
       Works Program.
Log in to download the original file

Attachment 1 - Q3 Operational Plan Update.pdf · 304 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.