Council archive · source document
Bill of Quantities · OPW24/0125
ITEM NO. DESCRIPTION UNIT QUANTITY RATE TOTAL
SECTION 2 : CLEARING & EARTHWORKS
2.1 Temporary fence around construction area m 166 16.40 $ 2,722.40
2.2 Selective clearing and grubbing to roads and allotments as directed. ha 1.08 6045.00 $ 6,528.60
2.3 (a) Strip topsoil 100mm thick, stockpile as required.
(Net solid volume of cut) m3 480 7.70 $ 3,695.76
(b) Respread topsoil 100mm thick to verges and distrubed areas as required.
(Net solid volume of cut) m3 251 17.00 $ 4,270.58
(c) Dispose of excess topsoil off site as required. (Net
solid volume of cut). m3 229 18.50 $ 4,232.02
2.4 Remove & dispose of redundant infrastructure and surplus material including Lump
concrete kerbing, driveway crossovers, road surfacing etc. $ 30,000.00
Sum
2.5 Remove & dispose of trees complete including removal, cartage, dumping, and
backfilling and trimming of area with on site material No 94 255.00 $ 23,970.00
2.6 Earthworks, No Bulking Factor (Net Solid Volume of Cut)
(a) On leads to Roads and Drains m3 794 15.20 $ 12,068.80
(b) Imported Fill (20% Bulking Factor) m3 1059 60.00 $ 63,540.00
2.7 Supply and install Design and Construct Sleeper retaining wall complete Lump
$ 25,000.00
Sum
2.8 Construction water Item 1 8000.00 $ 8,000.00
TOTAL SECTION 2
$ 184,028.15
EARTHWORKS
QUANTITIES ILLUSTRATED HEREIN ARE ESTIMATES FOR TENDERERS INFORMATION ONLY. TENDERERS ARE REMINDED THAT THIS IS A LUMP SUM CONTRACT AND ALL QUANTITIES MUST BE CONFIRMED BY THE
TENDERER IN THEIR TENDER SUBMISSION.
Page 3 of 6 STP24-0253 Estimate of Costs-Site Civil Works-Rev A.xls
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Bill of Quantities.pdfRelated documentApplication case desk ↗
About this file
- File size
- 122 KB (small file)
- File type
No other editions are linked here.