Page 8
5 STORMWATER QUANTITY
A roof and allotment drainage system has been designed to comply with:
1. AS/NZS 3500.3:2015 - Plumbing and Drainage Part 3: Stormwater Drainage;
2. The Queensland Urban Drainage Manual (QUDM), and;
3. The Noosa Plan Planning Scheme Policy PSP05.
5.1 Detention Assessment
The Stormwater Management Plan (SMP) prepared by SLR Consulting dated March 2018 (Ref No.
620.12292-R01) details a proposed detention tank arrangement required to ensure that the
proposed development will not worsen peak outflows from the proposed development area. The
detention requirements of the aforementioned SMP have been incorporated into the Siteworks and
Drainage Plans prepared by Morgan Consulting Engineers.
Refer to Appendix D for the Siteworks and Drainage Plans and Section 6 for the Stormwater
Quality Management assessment.
5.2 Proposed Drainage Patterns
The proposed drainage patterns are as follows (refer to Appendix D for the Siteworks and Drainage
Plans):
Roof Catchment:
1. Roofwater runoff from each proposed residential dwelling will flow via downpipes to a 3kL
water reuse tank with overflow to the internal drainage network, where it will be directed
to an underground detention tank prior to being discharged to the Lawful Point of
Discharge.
2. First flush roofwater runoff from the proposed hotel building will flow via downpipes to
the internal drainage network, where it will be directed to an underground detention tank
prior to being discharged to the Lawful Point of Discharge.
3. Roofwater runoff from the proposed hotel building, exceeding first flush, will flow via
downpipes to an underground 200kL water reuse tank, with overflow directed to an
underground detention tank prior to being discharged to the Lawful Point of Discharge.
Ground Catchment:
1. Surface runoff from the proposed residential properties and road surface will be collected
by the internal drainage network, where it will be directed to an underground detention
tank prior to being discharged to the Lawful Point of Discharge.
2. Surface runoff from the proposed hotel development will be collected by various
stormwater pits and flow to an underground 200kL water reuse tank, with overflow
directed to an underground detention tank prior to being discharged to the Lawful Point
of Discharge.
Site Based Stormwater Management Plan
Reconfiguration of a Lot and Mixed Use Development at 215 David Low Way, Peregian Beach
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.