Original source · versioned page text
Revised Civil Engineering Response Cover Letter
22.1 Sizing appears to be small given the land use change. This may be due to the low initial loss values adopted for pervious surfaces in the model. Provide further information of how rational method flows were calculated, including tc estimates. Provide, as a comparison, detention sizing based on QUDM recommended initial pervious loss rate of 20mm. 22.2 Provide survey for the existing drainage system that the detention tank will connect into (i.e. existing pit IL and pipe diameter and outfall IL). 22.3 The outlet structure from the detention tank is unclear. Is the final outlet an upstand 225 dia pipe as seems to be shown? If this is the case won’t the upstream orifices all be drowned? 22.4 Regardless of the above, for whatever outlet pipe is selected for the detention tank, demonstrate that the final outlet won’t drown the orifices and that the assumptions in the model will be met (eg. The outlet pipe from the tank should be set down lower than the lowest orifice so that it does not become drowned) 22.5 An access chamber to the detention basin outlet structure is shown and is supported. However why is the lid on this chamber shown as a grate rather than a sealed lid? Won’t the grate allow flows to bypass the detention tank? RESPONSE Item 21. From our analysis of Council assessment of Lot 5 Taylor Court, there appears the need for a detention basin on the subject site to account for high peak stormwater discharge to the downstream network. Unfortunately, we do not have the report or correspondence to confirm the downstream basin provides detention of flows to this site and from conversations with Council staff, are of the opinion it provides a water quality function only. If Council has access to this drainage study and basin design report, we would appreciate a copy. Despite this, it is acknowledged that any downstream basin structure will provide some form of flow mitigation to runoff entering the basin. Item 22.1. Rational method calculations were provided in Appendix C of the stormwater management report 2123-SBSMP-01. Tc is calculated using the friends eq’n for overland sheet flow from QUDM. Initial and continuing loses for the XP Storm model were then adapted to these Rational method results as per Tables 4.2 an 4.3 in the report and Figure 4.1. The pre-development rational method values were consistent with the XP Storm outputs however they were typically 5% less in magnitude so the existing case rational method results were used as the base case to compare against the post development (mitigated) XP Storm model results. This builds in a conservative 5% overdesign into the detention model. Item 22.2. It is recognised that The invert of the existing pit was not included in the original site survey. Barlow Shelley attended site to measure the depth of the SW pit and confirm it is 1.65m deep. This should be confirmed prior to construction but established that there is sufficient depth to reliably connect the stormwater system to this existing pit structure and outlet pipe. Item 22.3. The hydraulic orifice controls are mirrored into the wall of the riser pipe. This was not clear on the original plans so please refer to the updated drawing 2123/R07 (Rev C). Item 22.4. The outlet pipe from the tank exits the detention structure through the floor. The lowest pipe orifice is the tank invert so the system cannot become permanently drowned in function. There is a second maintenance access in the pipe riser and overflow area for maintenance to clear this space of debris if required. In the event this area is not maintained and a significant storm (or design storm grater than the 1% AEP) is experienced on site. A weir to the south side of the bioretention basin provides overflow redundancy so the drainage system inside the development site does not back up and enter the units. 2123 – 3 Taylor Court, Cooroy 4 CL/cl
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.