l Noosa Netserv Plan Planning Assumptions June 2024
Table 4 - DMaTT Development Constraints
Constraint Attribute Data source
Land Use Community Use, Outdoor Sport and Baseline land use layer
Recreation, Car parks, Cemetery, Park,
Shopping Centre and Council owned land via
“CannotDev” flag
Tenure CV, EA,RE,FR,NP, SF tenure QSpatial
Parcel type Easement, Road, Watercourse QSpatial
Local & Core Local & Core Koala Habitat Noosa Planning Scheme
Koala Habitat
Erosion prone Erosion prone area Noosa Planning Scheme
area
Coastal Coastal Protection & Scenic Amenity Noosa Planning Scheme
Protection &
Scenic Amenity
Coastal hazard High & medium risk storm tide inundation area Noosa Planning Scheme
- Storm Tide
MSES Matters of State Environmental Significance QSpatial
(fish habitat, wetlands, vegetation offsets,
marine park, protected areas, regulated
vegetation, wildlife habitat, koala habitat)
MLES Matters of Local Environmental Significance Noosa Planning Scheme
(wetland buffer, wetland, matters of local
environmental significance)
Extractive Separation area or resource processing area Noosa Planning Scheme
resources Exclusions:
Industry zone
Flooding • 1% AEP Noosa Planning Scheme
Overland flow Overland flow path (excluding built up areas/ Noosa Planning Scheme
path zones with existing stormwater infrastructure)
Heritage Areas Local & State heritage place Noosa Planning Scheme
Infrastructure Bulk water supply infrastructure buffer – 20m, Noosa Planning Scheme
Electricity supply substation buffer - 10m, High
voltage electricity line buffer, Lake Kurwongbah
setback – 80m, Lake Samsonvale and Lake
Kurwongbah setback – 400m, Landfill site,
Landfill site buffer - 200m, Property containing
bulk water facility, Pumping station buffer,
Wastewater treatment site, Wastewater
treatment site buffer - 400m, PIP road upgrade
buffer (15m from centreline) & road
investigation buffer (20m from centreline),
BHWA alignment and LGIP Future Trunk
Public Parks.
Industry zone exclusions:
Landfill site buffer - 200m
Wastewater treatment site buffer
• Sewer pump station buffer
Slope Slope greater than 20% 2014 LIDAR data
16
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.