2016-02-02 Infrastructure & Services Committee Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
INFRASTRUCTURE & SERVICES COMMITTEE MEETING AGENDA 2 FEBRUARY 2016
6 ELECTRIC BUS TRIAL UPDATE - JANUARY 2016
DOCUMENT INFORM AT ION
Author Project Officer, Joanna Ferris
Planning and Infrastructure Department
Index ECM\ Project\ TP000300
ECM\ Subject\ Commercial Bus Routes
ECM\ Subject\ Transport Levy
Attachments Nil
EXECUTIVE SUMMARY
Not applicable.
RECOMMENDATION
That Council note the report by the Project Officer to the Infrastructure & Services Committee
Meeting dated 2 February 2016 providing an update on the electric bus trial.
REPORT
The purpose of this report is to provide an update on the electric bus trial following the termination
of the original trial that was scheduled to commence in February 2016 with Patico Automotive Pty
Ltd as the electric bus supplier.
1. Contract Termination
The electric bus lease agreement with Patico Automotive Pty Ltd was terminated in November
2015 due to the contractor being unable to meet the required delivery date. The buses were
manufactured in the UK however, following testing, delays occurred as a result of technical issues
with the air conditioning system.
As the supplier could not meet the delivery date specified in the lease agreement, it was mutually
agreed that the agreement be terminated, and this was finalised in January 2016.
2. Department of Transport and Main Roads Support
The Department of Transport and Main Roads (TransLink) has confirmed that they remain
committed to the electric bus trial and will continue to support the trial as per the arrangements in
the existing Memorandum of Understanding.
TransLink are also supportive of the proposal to test the market on a satellite depot operation
based either at the Council Depot or a suitable site elsewhere in the Noosa area, subject to Sunbus’
support, and so long as it does not result in higher costs to the State during the trial.
This proposal has the benefit of reducing travel time from the current Marcoola depot thereby
increasing the range of the electric buses whilst servicing the route.
A further benefit of testing the market at this stage is that more electric bus manufacturers have
emerged since the original pre-feasibility study was undertaken in 2014. Additionally, battery
technology has improved which could mean greater range can now be achieved than previously.
Page 29 of 41
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.