INFRASTRUCTURE & SERVICES COMMITTEE MEETING AGENDA 2 FEBRUARY 2016
3. Fast Charge Infrastructure
Line marking has occurred in Diyan Street, Tewantin to allow for two electric buses to be fast
charged.
Two fast charge electric vehicle stations have been purchased and are currently stored at the
Noosaville Depot. The new Expressions of Interest electric bus specifications require the electric
buses to be compatible with the E-Station Cir Control Combination fast charger specifications.
4. Tender Process
Expressions of Interest for the electric bus trial will be advertised in early February with the
anticipated appointment of a Contractor in late February.
In order to reach a wide market, the tender will be advertised in the Australian Bus & Coaches and
the International Association of Public Transport publications.
5. Timeframes
February 2016 Appointment of electric bus contractor
March – August 2016 Procurement of electric buses
September – November 2016 Pre-trial testing of electric buses and charging infrastructure
December 2016 – May 2017 Six month electric bus trial (including two free holiday bus
periods at Christmas and Easter).
Previous Council Consideration
Ordinary Meeting Minutes, 9 April 2015, Item 4, Page 8
That Council note the report by the Director Planning & Infrastructure to the General Committee
Meeting dated 7 April 2015 and:
A. Note the pre-feasibility study report prepared by consultants GHD Pty Ltd, provided at
Attachment 1 to the General Committee report;
B. Based on the findings of the report, approve the commencement of a six month live trial of
electric buses in Noosa during the 2015/16 financial year:
1. In a 50:50 cost sharing partnership with the Department of Transport and Main Roads,
TransLink Division;
2. Covering the existing 627 Tewantin – Sunshine bus route;
3. Leasing up to 3 x Optare 10 metre electric buses based on the submitted pricing in the
GHD report; and
4. Facilitating the installation of suitable charging infrastructure to support the live trial.
C. Authorise the CEO to negotiate with TransLink, Sunbus and Optare regarding the
implementation, monitoring and reporting of the live trial; and
D. Approve the funding of the live trial to a maximum of $550,000 to be met from the Public
Transport Levy Reserve.
Finance & Risk
The funding for the trial will be met from the Public Transport Levy Reserve which currently stands
at $1.6 million.
TransLink has committed $480,000 towards the trial.
Page 30 of 41
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.