ATTCH 3 - IR Response - Erosion, Coastal Processes and Stormwater (Dr Trevor Johnson)

Attached to the e-mail RAL17/0501 IR Response email 2 of 4.

of 35

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (12.6 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Kenlynn Pty Ltd Report Number 620.12166-R01

Castaways Beach 3 November 2017
Stormwater Management Plan Version v0.1
Page 9

 

3 WATER QUALITY ANALYSIS
3.1 Overview

As discussed in Section 2.1, it is proposed to construct a basin(s) within each lot to receive the
stormwater runoff from that lot.

As demonstrated in Section 2.4, the basin(s) will be sufficient to capture the runoff from all events up
to and including the 1% AEP flood event

The performance of the basin(s) in treating the stormwater runoff from each lot was therefore analysed
using MUSIC.

3.2 MUSIC Model

A MUSIC model of a typical 1,000 m? allotment was setup, including the proposed bioretention basin
at the downstream end of the lot. The layout of the MUSIC model is shown in Image 2.

 

©)

Urban [Mixed]

 

 

 
 
   

 

Bioretention
Receiving Node

Image 2. MUSIC Model Layout

A mixed catchment approach was adopted, using six minute rainfall data from Cooroy station
(#40059) in the analysis, in accordance with MUSIC Modelling Guidelines (Version 1.0 — 2010).

The Urban node comprised an area of 0.1 ha, and a fraction impervious of 60%. Standard parameters
for the Rainfall-Runoff and Pollutant Concentrations were adopted, in accordance with the MUSIC
Modelling Guidelines.
The properties of the bioretention basin were as follows:

e High Flow Bypass = 0.082 m*/s

e Extended detention Depth = 0.3 m

e Surface Area = 100 m?

e Filter Area = 100 m?

e Unlined Filter Media Perimeter = 50 metres

SLR Consulting Australia Pty Ltd
Log in to download the original file

ATTCH 3 - IR Response - Erosion, Coastal Processes and Stormwater (Dr Trevor Johnson).pdf · 12.6 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.