13. Certification of the completed works within the 4.5m setback from the revetment wall
must be submitted to Council within 3 months of the completion of the works. The
certification must be prepared by a RPEQ (Registered Professional Engineer of
Queensland) and state that the works:
a. have not reduced the amount of available flood storage within the 4.5m setback
from the revetment wall;
b. have not negatively impacted the stability of the revetment wall or negatively
impacted the associated membrane;
c. have not reduced the available flood storage within the lot from the profile as
described in The Noosa Plan 2020 – Low Density Residential Zone Code; and
d. meet the relevant conditions of this approval.
Stormwater Drainage
14. Stormwater runoff from the development must be disposed of on-site without causing
scour or damage to the subject site or any adjoining property.
Damage to Services and Assets
15. Any damage caused to existing services and assets as a result of the development
works must be repaired at no cost to the asset owner at the following times:
a. Where the damage would cause a hazard to pedestrian or vehicle safety,
immediately; or
b. Where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and
assets must first be referred to the relevant service authority for approval.
5. REASONS FOR REFERRALN AGENCY’S DECISION
The proposal is subject to specific built form parameters outlined in The Noosa Plan (25
September 2020).
6. REFERENCE DOCUMENT
Plan No. Rev. Plan/Document Name Date
0447 – OW1.1 A Existing & Proposed Site Plan prepared by SCG 24 April 2025
Consulting
7. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form
part of the referral agency conditions:
Aboriginal Cultural Heritage Act 2003
1. There may be a requirement to establish a Cultural Heritage Management Plan and/or
obtain approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person
who carries out an activity must take all reasonable and practicable measures to ensure
the activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply
with the duty of care. Substantial monetary penalties may apply to individuals or
corporations breaching this duty of care. Injunctions may also be issued by the Land
and Resources Tribunal, and the Minister administering the ACH Act can also issue stop
Page 4 of 5
Document Set ID: 24491999
Version: 3, Version Date: 30/01/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Referral Agency Response - Planning RAP25 0023 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 117 KB (small file)
- File type
No other editions are linked here.