Retention of Existing Trees
8. The existing trees on adjoining properties must be retained and protected during construction
wherever achievable. To avoid doubt, this advisory note is not intended to exclude the
operation of Chapter 3 of the Neighbourhood Dispute Resolution Act 2011 following
construction of the development which is the subject of this development approval.
Removal of Existing Trees and Vegetation
9. Stockpiling mulch to the appropriate volume and separation is required for fire mitigation as
well as optimum weed seed sterilisation.
Qualified Person
10. Qualified Person, for the purpose of:
a. undertaking, supervising tree works and preparing arboriculture certification, is
considered to be a person with a minimum three years current experience in tree
protection, hazard identification/mitigation and AS2303:2018 assessment and either:
i. International Society of Arboriculture (ISA) certification; or
ii. A Diploma of Arboriculture.
b. managing Fauna protection is considered to be a certified Fauna Spotter Catcher.
c. preparing certification and managing declared plant pests, is considered to be:
i. a landscape architect with a minimum of 3 years current experience in the field
of pest plant management;
ii. a botanist or ecologist with a minimum of 3 years current experience in the field
of pest plant management; and
iii. an environmental consultant with a minimum of 3 years current experience in the
field of pest plant management.
Landscape Works
11. The applicant must pay the re-inspection fee in accordance with Council's Fees and Charges
Register where:
a. an inspection revealed that any constructed rehabilitation/landscape works do not
comply with the conditions of the Decision Notice, Approved Plans and or Approved
Documents
b. certification is submitted to Council falsely stating that works comply with the approved
plans, documents and or conditions of the Decision Notice.
12. Landscape structures must:
a. be certified by an RPEQ; and
b. have gained separate building approval
Environmental Advisory Notes
13. The Environmental Protection Act 1994 states that a person must not carry out any activity
that causes, or is likely to cause, environmental harm unless the person takes all reasonable
and practicable measures to prevent or minimise the harm. Environmental harm includes
environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
construction and landscaping phases of this development are to adhere to their ‘general
environmental duty’ to minimise the risk of causing environmental harm.
Erosion and Sediment Control
14. Accepted best practice standards include International Erosion Control Association
Australasia Best Practice Erosion and Sediment Control.
Page 18 of 19
Document Set ID: 23410526
Version: 6, Version Date: 14/01/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning OPW24 0125.pdfRelated documentApplication case desk ↗
About this file
- File size
- 3.2 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.