2019-02-18 General Committee Meeting Notes
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING 18 FEBRUARY 2019
A. Approve the application in accordance with the following conditions:
PLANNING
When Conditions must be Complied With
1. Unless otherwise stated, all conditions of this Decision Notice must be complied
with prior to the use commencing, and then compliance maintained at all times
while the use continues.
Approved Plans
2. Development undertaken in accordance with this approval must generally comply
with the approved plans of development. The approved plans are listed in the
following table unless otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
DA01 18 Site Calculations & Staging Plan, prepared by All 05-02-2019
Design and Drafting
DA02 18 Site Plan, prepared by All Design and Drafting 05-02-2019
DA03 18 Site Plan – Landscaping and Fencing, prepared by 05-02-2019
All Design and Drafting
DA04 18 Site Elevations, prepared by All Design and Drafting 05-02-2019
DA05 18 Site Elevations, prepared by All Design and Drafting 05-02-2019
DA06 18 Unit Type T1A, prepared by All Design and Drafting 05-02-2019
DA08 18 Unit Type T1B, prepared by All Design and Drafting 05-02-2019
DA09 18 Unit Type T2, prepared by All Design and Drafting 05-02-2019
DA10 18 Unit Type T3, prepared by All Design and Drafting 05-02-2019
DA11 18 Exterior Materials and Colours, prepared by All 05-02-2019
Design and Drafting
Performance Bond
3. Security in the form of a cash bond or trading bank guarantee to the sum of
$35,000 must be submitted to Council, to secure performance of all conditions of
this approval, prior to the issue of a Development Permit for Operational Works.
The cash bond or trading bank guarantee will be returned on performance of the
conditions of approval less any costs incurred by Council in respect of enforcing
performance of this permit. Council reserves the right to call upon the bond or
guaranteed sum to effect compliance with conditions.
4. The requirements of this development approval are to be effected, prior to the
use of the premises. Council reserves the right to call upon the bond or
guaranteed sum referred to in this approval to effect compliance with conditions.
Building Height
5. The maximum height of the development must not exceed 8 metres above the
finished ground level and the natural ground level.
6. Certification must be submitted to Council from a Licensed Surveyor which
certifies that the buildings do not exceed the maximum height requirement of this
Decision Notice.
Page 5 of 15