2508-47877 SRA - SARA response with conditions
Attached to the e-mail SARA response with conditions - MCU25/0090 and OPW25/0136.
2508-47877 SRA
ii. reinstate the kerb and channel;
iii. reinstate road pavement after closure and removal; and
iv. re-establish the pedestrian pathway.
5. (a) Provide a 2 metre noise barrier in the locations shown in the Prior to the
Acoustic Report, prepared by Acoustic Works, dated commencement of use
18/07/2025, with reference 2025219, and Revision R01A, and to be maintained
specifically within Figure 7: TMR Acoustic barrier – Level 1 and at all times.
Table 12: Recommended Acoustic Barrier Height.
(b) Design the noise barrier generally in accordance with Section 8.
Recommendations of the Acoustic Report, prepared by Acoustic
Works, dated 18/07/2025, with reference 2025219, and Revision
R01A and the following standards:
i. DTMR Traffic Noise Management Code of Practice,
Volume 1, Chapter 7 and technical Specifications
MRTS15;
ii. DTMR technical Specifications MRTS15 Noise Fences (as
amended by QR-CTS-Part 41);
iii. Queensland Rail Civil Engineering Standard Specification
QR-CTS-Part 41 – Design and Construction of Noise
Fences / Barriers; and
iv. DTMR Standard Drawings.
(c) Submit RPEQ certification to the North Coast Regional Corridor
Management team within the DTMR, via
[email protected] confirming that the
development has been designed and constructed in accordance
with part (a) and (b) of this condition.
State Assessment and Referral Agency Page 4 of 7