54. Only minor pruning will be permitted of existing tree branches protruding beyond the 10m
setback line under the supervision of the site arborist. The degree of pruning required will be
submitted for approval in conjunction with an application for operational works.
55. No earthworks (fill or cut or earth-spill) shall occur within the 10m intermittent creek setback
line.
56. Retaining walls are to be designed and constructed to provide bridging footing structures as
necessary to avoid root damage to retained trees.
57. Upper level pool and lookout earthworks are to be minimal in scale and extent and localised to
the footprint of the immediate construction. The pool is to be a maximum of 12m long by 4 in
size. Earthworks are to be temporarily screened from Hastings Street utilising black or dark
green shade cloth or equivalent material until construction work in this area is fully stabilised.
Disturbed soil in this area is to be fully stabilised within 10 business days of initial disturbance
with either a temporary or permanent treatment.
58. The fence colour of the upper level pool located to the east of Building B shall be non
reflective and charcoal/ woodland grey in colour. The retaining wall for the pool is to be clad in
dark coloured rock, with native plantings located in front of it to provide screening.
59. No shade structures or gazebo shall be erected at the lookout or upper level pool behind
Building B. Only black, dark brown or navy blue coloured umbrellas shall be used in the
vicinity of this pool.
60. Trees to be removed shall be in accordance with the approved plans.
61. Disturbance of the upper eastern area of the site to construct the boulder gabion walls shall
minimise the disturbance to existing native trees and their roots wherever possible. Suitable
techniques will be utilised to minimise disturbance and damage to this area. Rocks utilised will
be grey in colour, with non-reflective wire cages.
Environmental Management Plan
Preparation
62. An environmental management plan (EMP) for the Site shall be prepared and implemented by
persons holding appropriate environmental and construction engineering qualifications and
proven expertise in the preparation and implementation of EMPs, to ensure that the impact on
the environment of the carrying out of the Development is minimised, the Environmental
Values of the Site are protected and enhanced and the Development is ecologically
sustainable.
63. The EMP shall document in detail how compliance with the Conditions is to be achieved.
64. The EMP shall demonstrate a high level of environmental care and responsibility and be
consistent with best practice for developments of this type in similar environments.
65. The EMP shall detail the Developer’s environmental policy and the proposed environmental
management system for the Site.
66. The EMP shall specify to the reasonable satisfaction of the Manager – Land Development:
66.1 The performance targets, including those derived from the Conditions and other
requirements arising from legislation and other approvals;
66.2 how the performance targets are to be achieved;
66.3 who is responsible;
66.4 when the performance targets will be satisfied;
66.5 how performance will be monitored;
66.6 reporting arrangements;
Page 17 of 59
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Change to an Existing Approval - 010.2006.00000823.003 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 329 KB (small file)
- File type
No other editions are linked here.