220711 Noosa Oyster Project - CEMP

Attached to the e-mail Noosa Oyster Project _ Construction and Environmental Management Plan (CEMP).

of 50

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (13.4 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

3.               Implementation
     3.1.    Risk Assessment
         The risk to the environment of carrying out the project has been considered and documented

          Please see attached documentation
     3.2. Environmental Management Activities and Controls

            The following environmental management activities, mitigation and control measures will
            be adopted to prevent or minimise environmental impacts

         3.2.1.Air quality

                                                                                           Timing /
            Control Measure                                      Responsibility
                                                                                           Frequency
            Potential Impact: Emissions of air pollutants from motor vehicles, vessels & plant
            Regular maintenance of machinery.
                                                                                           Ongoing during
            Workers instructed not to leave machinery            Site Supervisor
                                                                                           project
            idling when not in use.
            Potential Impact: Dust generated from movement of plant and equipment
            Disturbance of site will be monitored and
                                                                                           Ongoing during
            the site will be restored prior to carrying          Site Supervisor
                                                                                           project
            out earthworks in new area.
            Excavated materials will be stocked piled
            and where possible re-used on site. Excess
                                                                                           Ongoing during
            materials to be disposed of in accordance            Site Supervisor
                                                                                           project
            with the Protection of the Environment
            Operations Act 1997.
            Where significant dust is generated, the                                       Ongoing during
                                                                 Site Supervisor
            work area will be watered down.                                                project

         3.2.2. Erosion and Sediment Control

                                                                                           Timing /
            Control Measure                                      Responsibility
                                                                                           Frequency
            Potential Impact: Site erosion and sediment laden water leaving the site
            Sediment and erosion control fencing will be
                                                                                           Ongoing during
            installed as required and left in place until all    Site Supervisor
                                                                                           project
            works are complete.




M&J Marine Services                                    Page 12                     Environmental Management Plan
Log in to download the original file

220711 Noosa Oyster Project - CEMP.pdf · 13.4 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.