220711 Noosa Oyster Project - CEMP
Attached to the e-mail Noosa Oyster Project _ Construction and Environmental Management Plan (CEMP).
The original of this document is very large (13.4 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Silt Booms will be deployed at build sites as
needed to control excessive plumes and
Ongoing during
turbidity caused by the reed construction. Site Supervisor
project
They will also be used on the load site as
needed
Erosion control measures will be monitored and Ongoing during
Site Supervisor
maintained throughout the project. project
After heavy rain, all sediment and erosion Ongoing during
Site Supervisor
controls will be checked and made good. project
3.2.3. Water Quality
Timing /
Control Measure Responsibility
Frequency
Potential Impact: Contamination of water due to chemicals, fuels or wastes
Storage of fuels, chemicals and wastes will Ongoing during
Site Supervisor
be clear of stormwater or drainage lines. project
Safety Data Sheet (SDS) of hazardous
Ongoing during
substance will be referred to when spills Site Supervisor
project
occur.
Work site will hold a spill kit to contain site Ongoing during
Site Supervisor
spills. project
All hazardous substances on site will be
Ongoing during
recorded in the Hazardous Substances and Site Supervisor
project
Safety Data Sheet Registers.
M&J Marine Services Page 13 Environmental Management Plan
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.