Original source · versioned page text
220711 Noosa Oyster Project - CEMP
Attached to the e-mail Noosa Oyster Project _ Construction and Environmental Management Plan (CEMP).
The original of this document is very large (13.4 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
General:
1. ESCP Refers to Erosion and Sediment Control Plan.
2. ESC Refers to Erosion and Sediment control
3.Sediment includes but is not limited to clay, silt, sand ,gravel, soil, mud, cement and ceramic waste
4.Any reference to IECA White books (2008) refers to IECA 2008 Best Practice Erosion and Sediment
control. Books 1-6 International Erosion Control (Australasia) Picton NSW
The ESCP:
5. The ESCP and its associated ESC measures shall be constantly monitored , reviewed and modified as
required to correct deficiencies. Council has the right to direct changed if, in its opinion the measures that
are proposed or have been installed are inadequate to prevent pollution.
6. Prior to any activities onsite the responsible person(s) is to be nominated. The responsible person shall
be responsible for ESC measures onsite. The Name ,address and 24 hour contact can be found within
the M&J marine Environmental Management plan which will be submitted to council. Council Shall be
advised within 48 hours of any changes to the responsible person(s), or their contact details, in writing
7. The approved ESCP shall be available on site for inspection by Council officers while work activities are
occurring
8. The implementation of the ESCP shall be supervised by personnel with appropriate qualifications and /
or experience in ESC on construction sites.
9. All ESC measures shall be appropriate for the sedate type of the soils onsite, in accordance with the
IECA white books or other current recognised industry standard for ESC for Australian conditions.
10. All works shall be carried out in accordance with the approved ESCP (as amended from time to time)
unless circumstances arise where;
A. Compliance with the ESCP would increase the potential for environmental harm; or
B. Circumstances change during construction and those circumstances could not have been
foreseen; or
C. Council determines that unacceptable off-site sedimentation is occurring as a result of a land
disturbing activity. In either case the person(s) responsible may be required to take additional,
or alternative protective action and/or undertake reasonable restoration works within the
timeframe specified by council.
11. M&J Marine shall ensure adequate supply of ESC, and appropriate pollution clean up materials are on
site at all times.
Site Access
12. The Site will be accessed by Hilton Esplanade, the sealed road will be monitored and swept clean daily
or as required if trucks are transferring sediment onto the road.
ABN: 766 242 991 45 Page 2 [email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.