Site Monitoring
13. The ESC will be monitored daily by the designated person(s)
14. The designated person must ensure that if a > 50% probability of rain event of >20mm (surface water) is
expected through a Bureau of Meteorology forecast over a 24 hour period, or if a short term pulse event
such as a thunderstorm occurs environmental controls are inspected and adapted to withstand the event
and remain effective.
15. The designated person must ensure that any disturbed areas are stabilised and rehabilitated as soon as
construction work is completed. Land based sediment and erosion controls must stay in place and be
maintained until the site is completely stabilised
Proposed Erosion and sediment controls to be in place on load site
Symbol Technique
Floating Silt Boom
Sediment Fence Barrier
ABN: 766 242 991 45 Page 3 [email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.