220711 Noosa Oyster Project - CEMP

Attached to the e-mail Noosa Oyster Project _ Construction and Environmental Management Plan (CEMP).

of 50

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (13.4 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

   2.4. Approval and Licensing Requirements
         Licences, permits and approvals required for this project are summarised in Table 2.2
         below. SMADS will ensure that any licences, permits and approvals are obtained prior to
         work commencing. A copy of all licences, permits and approvals are included in
         Attachment 1 of this EMP.
         Table 2.2 Summary of Licences, permits and approvals

              Regulatory       Licence / Permit /                     Summary of Key Conditions
                                                            Status
              Authority         Approval Type                          and Monitoring Required
                                                                     All works must be undertaken in
                                  Development                        accordance with Best Practice
          Noosa Council                                   Approved   Erosion and Sediment
                                   application
                                                                     Control (BPESC)

                                                                      Hold appropriate DA approvals
          Department of            Resource
                                                                     and comply with all conditions,
          agriculture and          Allocation             Approved
                                                                     reefs to be designed to minimise
             fisheries             Authority
                                                                        impact on existing habitat




   2.5. Environmental Training
         All M&J Marine workers who will be working on site shall receive site-specific induction
         training. The induction training will include:

          •     familiarisation with the requirements of this EMP;

          •     environmental emergency response training; and

          •     familiarisation with site environmental controls.

         M&J Marine may combine the Work Health and Safety (WHS) and Environmental
         induction into one. A record of the site induction will be made on the Site Environmental
         Induction Register (see Attachment 2).



   2.6. Emergency Contacts and Response
         This EMP sets out M&J Marines management of environmental emergencies during the
         project. It includes:

          •     the names of key emergency response personnel and contact details (including all-
                hours telephone numbers);
M&J Marine Services                                  Page 8                Environmental Management Plan
Log in to download the original file

220711 Noosa Oyster Project - CEMP.pdf · 13.4 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.