Original source · versioned page text
Annex 13 - Schedule 3 - Prescribed Tidal Works
Attached to the e-mail DA Application - Noosa Oyster Project (2 of 3).
Coastal Protection and Management Regulation 2017
Schedule 3. Code for Assessable Development that is prescribed tidal works
Part 3 Performance outcomes and acceptable outcomes
Character and amenity (generally)—prescribed tidal work not in a canal
2.1 Prescribed tidal works not in a canal are The design and construction of the prescribed tidal works is Complies with Performance Outcome 2.1. Due to the
compatible with their location, having regard toconsistent with the following standards— nature of the project the nominated Acceptable
the following— (a) subject to paragraph (d), prescribed tidal works do not Outcomes are not considered to be suitable but have
(a) the character and amenity of the works’ extend past the side boundary or extended side boundary of the been considered.
immediate surroundings and the locality within lot connected to the works;
which the works are located; The works are to restore rock oyster ecosystems
(b) subject to paragraph (d), prescribed tidal works are the only throughout the Noosa River estuary that meet site
(b) if the relevant planning scheme states the works of their type along the edge of the tidal water fronting the suitability criteria and positively interact with current
desired character or amenity for the works’ lot connected to the works; human uses. As the Noosa River was historically
immediate surroundings or the locality within characterised by significant oyster ecosystems, they
which the works are located—the stated (c) subject to paragraph (d)—
are considered to be consistent with the character and
desired character or amenity. (i) for prescribed tidal works for a private purpose—the works
amenity of the works’ immediate surroundings and the
are not roofed; or
locality in which the works are located. Restoration
(ii) for prescribed tidal works for a non-private purpose—the Zones have been developed based on Habitat
works are not roofed unless they are the main access to land; Suitability parameters and Restoration Suitability
parameters as detailed in the Project Restoration Plan.
(d) if a relevant planning scheme standard is more stringent
than the standard mentioned in paragraph (a), (b) or (c)—the (a) The Restoration Zones include large areas of the
relevant planning scheme standard, to the extent it is more Noosa River and as such are adjacent to multiple Lots.
stringent than the standard mentioned in paragraph (a), (b) or
(c); (b) The Works are expected to be implemented
progressively with Phase 1 currently planned and
(e) any other relevant planning scheme standard that is not Phase 2 to occur over time as funds become available.
inconsistent with the standards mentioned in paragraphs (a) to As such, Phase 2 could include extension of Phase 1
(d). reef habitat which could include placement of
additional works of their type adjust to the frontage of
the same lots as Phase 1.
(c) The works are not roofed.
2
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.