               Vegetation Protection & Preservation
               70.    All Class 1, Class 2 and Class 3 pest plants declared under the Land Protection (Pest and
                      Stock Route Management) Act 2002 are to be controlled on the site prior to Council
                      endorsement of the plan of survey. In this context “controlled” shall mean, for class 1 and 2
                      pests, completely eradicated. For class 3 pests it shall mean removal of the plants where
                      they threaten environmentally significant areas of the site such as riparian zones and areas
                      of natural vegetation. Where class 3 plants are removed as a result of this condition and
                      there is not sufficient natural regeneration of native species, the areas shall be replanted with
                      endemic native species so that a sustainable natural ecosystem is restored.
                      Council’s Conservation Management Supervisor will not inspect the site until 30 days after
                      the weed treatment and replanting is complete.
               71.    Vehicular pavements within the drip zone of any of the existing trees on site to be retained
                      shall be designed as a pervious pavement (such as grass paving cells or similar), as this will
                      allow water that falls on this surface to penetrate to the trees root system. The pavement
                      shall be constructed so as not to damage the tree or their root system and in this regard
                      temporary fencing shall be provided around the trees during construction to help protect
                      them.
                      Plans shall be submitted to the Council for approval that clearly show the type and extent of
                      the pervious pavement and the temporary fencing prior to obtaining a Development Permit
                      for Operational Works.
               72.    Where retained tress are located in areas proposed to filled on site (or are located on
                      neighbouring allotments to the actual site to be filled), there will be a need to prevent fill
                      material from being placed on the trees root system. To this end the design of the filling
                      works will need to incorporate terracing around the tree or a similar means of ensuring that
                      the natural ground level around the trees remains generally the same as existing. These
                      measures shall clearly be shown on the plans submitted for Operational Works approval and
                      any drainage required to drain these areas shall also be shown on the plans.
               Contributions Towards Council Infrastructure
               73.    Monetary contributions shall be paid to Noosa Council towards the cost of providing and/or
                      upgrading various infrastructure at the rates applicable at the time of payment. An estimate
                      only of the contribution amounts under the current Council policies and requirements is
                      outlined in the table below:

                                                                                                    Amount:
                        Contribution Required For:
                                                                                      Stage 1       Stage 2        TOTAL

                        PSP12 – Public Open Space Contributions (Park)                    -            -               -

                        PSP16 – Sewerage Headworks Contributions                        $1,318       $34,270         $35,588

                        PSP17 – Water Supply Headworks Contributions                    $4,892      $127,204        $132,096

                        PSP20 – Pathway Trunk Network Contributions                       $703       $18,271         $18,974

                        TOTAL Contribution Amount =                                    $ 6,913      $179,745       $ 186,658

                        Please note, that these amounts are all subject to variations in the Consumer Price Index, All Groups
                        Brisbane from JUNE 2008 until the date of payment.

                      All contributions must be paid prior to Council endorsement of the plan of survey.




                                                                                                              Page 11 of 19
Document Set ID: 24764739
Version: 6, Version Date: 18/05/2026

Used in these records

About this file

File size
216 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval - 132007.2399.03 (AS PUBLISHED).pdf · 216 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.