Attachment C - Current DA MCU15.0111 · MCU15/0111.03

of 57

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Noosa Council documents




                                                                                                          MCU15/0111


                              Building and Construction Industry (Portable Long Service Leave) Levy
                      2.      The QLeave levy must be paid prior to the issue of a development permit where it
                              is required. Council will not be able to issue a Decision Notice without receipt of
                              details that the Levy has been paid. QLeave contact: 1800 803 481 (free call) or
                              (07) 3212 6855.
                              Qualified Person
                      3.      For the purpose of preparing a Geotechnical Report, and for certifying geotechnical
                              stability for the development, a qualified person is considered to be a person who:
                              a.       is a Registered Professional Engineer of Queensland (RPEQ); and
                              b.       has a degree in civil engineering or engineering geology; and
                              c.       has a minimum of 5 years experience in the field of geotechnical engineering
                                       or engineering geology.
                              Preparation of a Preliminary Construction Management Plan
                      4.      A preliminary Construction Management Plan must be submitted with the
                              Operational Works application and must address the following:
                              a.       traffic management during all aspects of the construction phase including:
                                       i.     a Traffic Management Control Plan in accordance with the Manual of
                                              Uniform Traffic Control Devices (MUTCD) detailing all temporary
                                              signage and traffic control measures prior to construction
                                       ii.    maintenance of safe pedestrian access for the areas affected by the
                                              works during and after daily construction has ceased
                                       iii.   proposed fencing to the site during the construction phase of the
                                              development
                                       iv.    approval of the Traffic Management Control Plan by the Department of
                                              Transport and Main Roads (DTMR) for any works on State controlled
                                              roads
                                       v.     provision for worker car parking
                              b.       maintenance and protection of water quality and existing drainage lines
                                       through the construction site, through the implementation of appropriate
                                       erosion and sediment control measures
                              c.       works programme identifying key components of the works and their
                                       respective durations
                              d.       establishment of a communication protocol with the general public, adjoining
                                       owners, emergency services and local businesses to advise of agreed
                                       construction times, impacts on traffic, services and other relevant issues
                              e.       identification of complaint management procedures including:
                                       i. contact details for the on-site manager
                                       ii. dispute resolution procedures
                              f.       details on the location of external fill sites/sources, the haulage route, type of
                                       vehicle to be utilised during filling operations and frequency of usage. NB any
                                       damage to the existing road system as a result of haulage operations shall
                                       be fully repaired at the applicant’s expense




                                                                                                               Page 17 of 37


Document Set ID: 20103451
Version: 1, Version Date: 25/07/2016                                                                        Print Date: 25 July 2016, 3:34 PM

Used in these records

About this file

File size
8.1 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment C - Current DA MCU15.0111.pdf · 8.1 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗