                                                                                        2008/658



      The design pavement thickness, together with CBR test results shall be submitted to Council’s
      Manager, Land Development for approval prior to placement of pavement material.
4.    Council’s Construction Technical Officer (ph 0410 512 505) shall be given seven (7) days’
      notice of intention to commence works to arrange a “pre start” meeting prior to the
      commencement of works.
5.    The principal contractor must have all the appropriate insurance and public liability
      documentation to carry out the works. The principal contractor is also responsible to ensure
      that any sub contractors also have the appropriate insurance and public liability
      documentation.
6.    Prior to the “pre start” meeting, the principal contractor must be provided with a copy
      of Council’s signed approved drawings and conditions by the applicant.
7.    The Consulting Engineers for the project shall be currently Registered Professional Engineers
      of Queensland (RPEQ).        The consulting engineers are responsible for arranging all
      inspections with Council’s Construction Technical Officer or nominated staff. Council’s
      Construction Technical Officer shall provide an inspection form for signing off by the Engineer
      at appropriate stages of construction, during on-site meetings. Construction Technical Officer
      will also sign the form at each stage when requested conditions have been satisfied. The
      works will be accepted “On Maintenance” after this form, signed by the inspector for each
      stage is complete, together with a letter from the Engineer requesting that the works go “On
      Maintenance”.
8.    Prior to works commencing, Council is to be advised of the Engineer (RPEQ) supervising the
      project. (This person will be the contact for the project).
9.    An inspection is to be carried out with the relevant Council officers, the Contractor and
      Supervising Engineer after road centrelines have been established. This inspection is to deal
      with the limits of clearing to be carried out for this development. This meeting is to take place
      prior to the “Pre-start” meeting.
10.   Council standards shall apply to these works unless otherwise modified herein.
11.   The person acting on this permit shall ensure that its consultants and contractors take all
      reasonable care during the construction of the engineering works to ensure that Council
      property, road pavements or facilities (such as underground drainage, water supply,
      sewerage, footpaths, kerbing, landscaping, street furniture, etc) are protected against any
      damage or interference whatsoever.
      If any Council property or facilities should be damaged by the Applicant or any of its
      Consultants or Contractors through any cause whatsoever in the course of, directly or
      indirectly, carrying out the engineering works, the Applicant and/or its Contractors shall
      forthwith notify the Manager Land Development and shall forthwith rectify the damage to that
      property or facility at its cost and to the satisfaction of the Manager Land Development.
      All rectification works are to be completed prior to the sealing of the survey plan or,
      alternatively, the Applicant may request Council to carry out the rectification work at the
      Applicant’s cost, such cost being paid by the Applicant to Council prior to the sealing of the
      survey plan.
      In the case of any emergency, Council shall be entitled to rectify such damage at the cost of
      the Applicant, such cost being paid prior to the sealing of the survey plan.
12.   The development of the site shall be carried out in such a manner as to prevent dust and/or
      sand nuisance to residents and/or tenants in the vicinity of the development.
13.   Construction work and other associated activities are permitted only during the hours of 7.00
      am and 6.00 pm Monday to Saturday. No work is permitted on Sundays or public holidays,
      except where extended hours are approved by the Manager, Land Development, or his
      nominee.
                                                                                     Page 2 of 10

Used in these records

About this file

File size
70 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 010.2008.00000658.001 [As Published].pdf · 70 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.