22.   Notwithstanding that Council has checked the plans with due care, where it is found during
      construction that variations from Council's standards exist, then Council standards shall apply.
23. WATER SUPPLY and SEWERAGE INFRASTRUCTURE APPROVAL CONDITIONS
This Decision Notice is issued subject to and conditional upon the relevant Approved
Development Permit having been granted to the applicant.
1.   A copy of the job specification is to be provided to Council’s Inspector within seven (7) days of the
     date of this Decision Notice, and prior to commencement of works.

2.    The names of any proposed contractors for works are to be submitted in writing, together with
      copies of current Public Liability and Workers Compensation Insurances together with certificates
      of currency for those policies, for consideration by the Assessment Manager seven (7) days prior
      to        pre-start         meetings          and         commencement           of         works.
      A separate letter will then be issued approving the contractor (or otherwise) for the works. No
      other contractor or subcontractor shall be engaged to carry out the works or any part of the works
      without the written approval of the Assessment Manager.


3.    Council’s Water & Sewerage Inspector shall be given (7) days notice of intention to commence
      works. A pre-start meeting shall be arranged prior to commencement of works by contacting
      Council’s Water & Sewerage Inspector, Mr Trevor Mourilyan, Ph. 0417 780 830. Inspector is only
      available for pre-start meetings, inspections and testing etc. between the hours of 6:30am to
      4:00pm, Monday to Friday. Inspector will not be available outside these hours unless prior
      approval is obtained from the Water & Sewerage Capital Works Manager with any costs incurred
      by Council outside the hours nominated above, met by the Contractor/Developer. These costs
      will be in addition to normal inspection fees.

4.    Notwithstanding that Council has checked the plans with due care, where it is found during
      construction that variations exist with Council's standards, Council standards shall apply.


5.    It is the responsibility of the applicant to ensure that its consultants and contractors take all
      reasonable care during the construction of the engineering works to ensure that Council property
      or facilities (such as underground drainage, water supply and sewerage) are protected against
      any damage or interference whatsoever.
6.
      If any Council property or facilities should be damaged by the applicant or any of its consultants or
      contractors through any cause whatsoever in the course of, directly or indirectly, carrying out the
      engineering works, the applicant and/or its contractors shall forthwith notify the Assessment
      Manager and shall forthwith rectify the damage to that property or facility at its cost to the
      satisfaction of the Assessment Manager prior to the sealing of the survey plan and/or acceptance
      of the works on-maintenance. Alternatively, the applicant may request the Council to carry out
      the rectification work at the applicant's cost, such cost being paid by the applicant to the Council
      prior to the sealing of the survey plan and/or acceptance of the works 'on maintenance' provided
      that in the case of emergency, the Council shall be entitled to rectify such damage at the cost of
      the applicant such cost being paid prior to the sealing of the survey plan and/or acceptance of the
      work 'on maintenance'.

7.    The Contractor shall make all necessary arrangements for supply of water required for
      construction works. The use of hydrant standpipes on Council mains will NOT be permitted.
      Contractors should contact Council’s Water Section on phone 5449 5254 to obtain an application
      form for issue of a key to access Council’s water tanker filling stations. Conditions of access and
      location of filling stations are detailed on the application form.



                                                                                        Page 4 of 10

Used in these records

About this file

File size
70 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 010.2008.00000658.001 [As Published].pdf · 70 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.