Decision Notice - 010.2009.00000945.001 [As Published] SUPERCEDED · 142009.945
2009/945
b. Damaged kerb and channel shall be replaced with ‘barrier’ type not ‘roll over’ as
indicated on drawing 09541-C1E.
c. At completion of construction the vegetation buffer shall be restored, between the tennis
court and property fence, with similar endemic tree species that previously existed in
this location.
3. Access to proposed netball courts:
a. The existing bikeway/footpath in Bicentennial Drive must remain open and clear of any
obstructions.
b. All sediment control devices shall be located within the school property.
4. A Traffic Management Plan (TMP) for the development addressing all construction phases
shall be prepared by suitably qualified persons and submitted to Council for approval prior to
the pre start meeting. The TMP shall address, but not be limited to, all items listed below, and
shall be flexible in that it addresses all stages of the development:
4.1. The nominated accesses location to and from the site.
4.2. The plan should detail the routing of trucks to and from the site.
4.3. Delivery vehicles and trucks to the site should only operate outside the peak school
drop off and pick up times namely 8.00am to9.00am and 2.30pm to 3.30pm.
4.4. Provision of onsite parking for personnel working on this development, as there is
limited parking available in adjacent streets, especially at the school peak times.
4.5. Provision of safe cycle and pedestrian movements in the vicinity of the development on
Bicentennial Drive and the Bicentennial Hall car park area.
4.6. No queuing of trucks is permitted on residential streets, especially prior to 7.00am.
Further parked trucks must have engines turned off.
4.7. Provision of signage and traffic controllers in accordance with Manual of Uniform Traffic
Control Devices and Transport Infrastructure (Roads) Act.
4.8. Provide an indication where the surplus spoil is to be transported to, and/or source of
imported fill material.
5. Suitable sediment control devices ("in pit” pollution control devices) shall be temporarily
installed into the first existing external downstream stormwater structure.
These devices are to be checked and cleaned on a regular basis and specifically after each
rain event.
These devices are to remain in place during the civil works and construction phases of the
development.
The location and type of device to be installed shall be established at the “pre start” meeting
with Council’s Construction Technical Officer and shall be installed prior to the
commencement of any works.
6. A site control and/or compliance bond of $3000 Officer to determine amount specific to
application is to be submitted to Council prior to the pre-start meeting. The pre-start meeting
will only be held once Council's Construction Technical Officer has confirmation that the bond
monies have been received by Council.
The bond will be refunded less any costs incurred by Council in ensuring compliance with
these conditions or any additional inspections incurred for substandard work or work
undertaken not in accordance with this permit.
Page 2 of 7
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2009.00000945.001 [As Published] SUPERCEDEDRelated documentApplication case desk ↗
About this file
- File size
- 57 KB (small file)
- File type
No other editions are linked here.