16. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Earthworks and Retaining Walls
17. All earthworks and associated batters must be undertaken in accordance with an Operational
Works approval, and contained entirely within the subject site unless written permission from
the respective landowner(s) is provided to Council.
Damage to Services and Assets
18. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
ENVIRONMENTAL MANAGEMENT
Land Rehabilitation
19. A vegetation protection covenant must be registered against the title of the property over the
land area identified as riparian protection on the western side of the waterway as well as the
10 metre wide rehabilitation area on the eastern side of the waterway pursuant to Section
97A of the Land Title Act 1994. The covenant document and a survey plan must be submitted
to Council for endorsement prior to lodgement with the relevant titles authority for registration
of title. The covenant document must:
a. incorporate the requirements of this Decision Notice
b. include Noosa Council as Covenantee.
c. reference Queensland Land Title Registry Standard Terms Document No. 715597513
Works within Protected Land
20. The following works must be undertaken within the covenant area in accordance with the
conditions of this approval prior to the submission of the sealing of the survey plan:
a. Control of pest plants listed in Planning Scheme Policy 2 Landscaping and Councils
Biosecurity Plan 2020 pest plants listed in Schedule 1 part 3, Schedule 2 and non -
scheduled invasive species;
b. Removal of any structures, debris or materials foreign to a natural environment
c. Rehabilitation and restoration to achieve the equivalent floristic composition of the pre
clearing undisturbed regional ecosystem as per the rehabilitation areas .
d. The planting of canopy species with local provenance in Regional Ecosystem 12.3.14a,
including threatened Eucalyptus conglomerata. The trees must be planted at a ratio of
1 tree per every 10m².
The works must be undertaken in accordance with an Operational Works approval.
21. The land area 30 metres west of the defined waterway bank and 10 metres east of the
defined bank of the waterway must be rehabilitated and revegetated and removed of all weed
species listed in the following standards and legislation:
a. Control of pest plants as listed in Planning Scheme Policy 2 Landscaping and Council’s
Biosecurity Plan 2020 pest plants listed in Schedule 1 part 3, Schedule 2 and Non-
scheduled invasive species; and
b. The works must be undertaken in accordance with an Operational Works approval.
Page 9 of 13
Document Set ID: 22511485
Version: 7, Version Date: 31/07/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.