Original source · versioned page text
Amended Negotiated Decision Notice RAL20-0021 [As Published]
28. Any retaining walls/structures must be wholly contained thin the lot they support.
29. All retaining walls must be designed and constructed in accordance with the planning scheme
and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
safety fence.
Damage to Services and Assets
30. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
Landscaping Works
31. The development site must be landscaped. The work must be undertaken in accordance with
an Operational Works approval and the Noosa Plan for that specific area and must include
in particular:
a. Provision of 15 street trees along the frontage of the Lots with a minimum pot size of
45 litres planted within the road reserve, excluding the head of the cul-de-sac.
b. Provision of turfed area to road frontages
All landscape works must be established and maintained over the one-year maintenance
period and in a manner that ensures healthy, sustained and vigorous plant growth.
32. All landscape works must be established and maintained over the one-year maintenance
period and in a manner that ensures healthy, sustained and vigorous plant growth.
33. Deleted
Fauna Management
34. Vegetation must only be removed or disturbed in accordance with a Fauna Management
Plan (or part thereof) prepared by a qualified person* and endorsed through an Operational
Works approval.
*(Refer to Advisory Note)
Vegetation Management
35. An arborist’s report is to be submitted for approval as part of the operational works
application. The purpose of the arborist’s report is to identify the native vegetation to be
retained on site, whilst recognising the need for vegetation clearing to occur in order to carry
out the development. The vegetation to be retained must be clear of proposed services, not
present a nuisance to neighbouring properties and be generally suitable for the proposed
location. The report is to be prepared by a suitably qualified person*.
(*Refer Advisory Note)
Rehabilitation works of Waterway and Park
36. Rehabilitation works must be undertaken in accordance with an Operational Works approval
and Planning Scheme Policy - PSP 2 Landscaping. An ecological rehabilitation plan must be
submitted, prepared by a suitably qualified person* (* refer Advisory Notes) for the waterway
and park area and must include in particular:
a. Rehabilitation of the Waterway – the area to be rehabilitated must be generally 5m
form the centreline of the waterway; from the new road south of Lot 15 to the creek in
Lot 99 in RP881300 as shown on drawing number 2035-01 (Master Layout & SWMP
Plan 1 of 3) Rev E dated 16.04.2021.
Page 6 of 19
Document Set ID: 21606483
Version: 1, Version Date: 07/09/2021
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.