Original source · versioned page text
Amended Negotiated Decision Notice RAL20-0021 [As Published]
b. Mature vegetation within the waterway corridor must be retained in situ if possible,
unless required to be removed for the construction of the natural channel (waterway)
south of Lot 15, or where vegetation poses a risk. Where vegetation is required to be
removed to reduce safety risks this request is to be supported by a written report from
a qualified person
c. Retention of existing bed and banks of the waterway unless required to be modified to
ensure function of the approved stormwater system, which may include reshaping into
a vegetated swale with stone low flow base and vegetated banks with coir mesh.
d. The waterway must be rehabilitated to reflect natural function and form, and include
riffles and ponds to provide variability in flow depth and refugia for fauna to live in during
dry periods.
e. details of the treatment to all batters, armoury, plantings, weed treatment, location of
services/utilities and rehabilitation.
f. Retention of significant trees within the park area to provide roost and forage values
for fauna, whilst ensuring a monoculture of Gympie Messmates (Eucalyptus cloeziana)
is not retained.
g. Revegetation of the park area, including the detention basin, ensuring plantings
maintain sufficient separation from the proposed pathway in the park, using a
staggered growth forms, grading from grasses , shrubs through to trees either side of
the pathway, where applicable.
h. a species palette and densities table incorporating the species selection of only native
local species suitable for the site
i. a maintenance period of no less than 3 years for the park area (Lot 100 and waterway
area in Lot 99)
j. measurable and achievable criteria on which the performance of the floristic and
structural component of the re-vegetation strategy can be assessed annually over three
years, including no weeds at the end of the rehabilitation period
k. control of all weeds species listed in the following standards and legislation:
i. Scheduled plants under the Noosa Biosecurity Plan 2020
ii. Undesirable Plant Species listed in Table SC6.3.5.1 of the Planning Scheme
Policy 2 Landscaping of the Noosa Plan 2020
iii. Council Listed Environmental Weeds, Exotic Grasses and other plants identified
in writing by Council
37. All rehabilitation and re-vegetation of the waterway and park must be completed prior to
Council endorsement of the Plan of Survey.
Page 7 of 19
Document Set ID: 21606483
Version: 1, Version Date: 07/09/2021
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.