Amended Negotiated Decision Notice RAL20-0021 [As Published]

of 19

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

                      b.      maintenance and protection of water quality and existing drainage lines through the
                              construction site, through the implementation of appropriate erosion and sediment
                              control measures
                      c.      works programme identifying key components of the works and their respective
                              durations
                      d.      establishment of a communication protocol with the general public, adjoining owners,
                              emergency services and local businesses to advise of agreed construction times,
                              impacts on traffic, services and other relevant issues
                      e.      Include a post out to the local residents and businesses advising of the proposed
                              development, the expected time frames and the site contact details.
                      f.      Include signage in prominent locations on the boundaries of the site advising of the
                              proposed development, the expected time frames and the site contact details.
                      g.      identification of complaint management procedures including:
                              i.       contact details for the on-site manager
                              ii.      dispute resolution procedures
                      h.      details on the location of external fill sites/sources, the haulage route, type of vehicle
                              to be utilised during filling operations and frequency of usage. NB any damage to the
                              existing road system as a result of haulage operations shall be fully repaired at the
                              applicant’s expense
                      i.      it is acknowledged that the preliminary Construction Management Plan will be a draft
                              document requiring finalisation upon appointment of the Principal Contractor employed
                              to construct the works and a final document will be required to be submitted at the Pre-
                              Start Meeting for the project.
                      Infrastructure Charges
               4.     All developments and/or changes to existing developments may require payment of
                      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                      made pursuant to the planning legislation and regulations current at the time of issue. For
                      further       information,     please        refer to https://www.noosa.qld.gov.au/planning-
                      development/development-tools-guidelines/infrastructure-charges
                      Qualified Person
               5.     For the purpose of preparing a Landscape Plan, a qualified person is considered to be a
                      landscape architect, landscape designer and/or horticulturist with a minimum of 3 years
                      current experience in the field of landscape design.
               6.     For the purpose of preparing an Arborist Report, a qualified person is considered to be a
                      person with either:
                      a.      ISA certification; or
                      b.      a Diploma of Arboriculture; and
                      c.      a minimum of 3 years current experience in the field of arboriculture.
               7.     For the purpose of preparing a Rehabilitation Plan, a qualified person is considered to be a
                      landscape architect, Environmental Engineer or ecologist with a minimum of 3 years current
                      experience in the field of landscape design.
               8.     For the purpose of preparing a Fauna Management Plan, a qualified person is considered to
                      be an ecologist with a minimum of 3 years current experience in the field of fauna assessment
                      and management.




                                                                                                         Page 9 of 19
Document Set ID: 21606483
Version: 1, Version Date: 07/09/2021
Log in to download the original file

Amended Negotiated Decision Notice RAL20-0021 [As Published].pdf · 418 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.