PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA 9 JUNE 2020
Building Appearance
5. The development must be finished with subdued/muted external building colours, as
shown on the approval plans.
6. Roof materials must be non-reflective to minimise the visual impact of the
development.
7. Any fencing must be designed and be of a colour that blends with the environment
and complements the building design.
8. Any waste bins or air conditioning units must be suitably screened so they are not
visible externally to the site.
Lighting
9. External light sources utilised on site are limited to an external light outside the front
door of the facility and a single dock light, used for a maximum for 30 minutes during
operation start and finish times outside of daylight hours.
Stormwater
10. All stormwater run-off from the new works is to be connected to the existing on-site
drainage system.
DEMOLITION
Works
11. Any demolition works must be undertaken in a manner that causes no detrimental
effect upon the amenity of the neighbourhood by reason of the creation of excessive
noise, lighting, air-borne hazards, atmospheric pollutants (including dust or odours)
nuisance or any other emissions in accordance with the nuisance provisions of the
Environmental Protection Act 1994.
Waste management
12. A Waste Management Plan (demolition) must be submitted in accordance with
Planning Scheme Policy 11 - Waste Management Plan and approved by Council’s
Waste Coordinator prior to issue of a development permit for Building Works for
demolition, removal or relocation.
The purpose of the Waste Management Plan is to facilitate the segregation of waste
for the effective reuse and recycling of such materials. Segregated wastes attract
significantly reduced disposal fees at the landfill with some items free. Higher gate
fees are charged for mixed waste.
Waste storage areas must provide for adequate separation of all reusable, recyclable
and waste materials. These must be located so that they are convenient and safe to
use.
The Plan must contain the following information:
a. The areas for the storage and separation of waste shown on a site plan;
b. A waste management table as indicated below is to be completed showing how
waste material is to be segregated - recycled – reused or disposed; and
c. Table – Waste Management Table
Page 5 of 55
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.