41. Infrastructure including reticulated water, sewerage, stormwater, and electricity are to be protected from
damage and made safe to the standard required by the regulatory authority;
42. All infrastructure must be disconnected, capped or sealed including:-
electricity meters removed and electrical wires disconnected; and
telephone lines are disconnected; and
high speed data cables and television provider boxes are disconnected and removed to the
standard required by the regulatory authority;
43. All building materials containing asbestos, including asbestos cement sheeting or roofing and lagging,
must be removed from the building and disposed of in accordance with industry best practice.
44. Waste generated during construction must be stockpiled in a centralised location and covered as required
to prevent material being blown onto adjoining properties including the road reserve or food waste from
generating vermin. All site waste must be disposed of to an approved waste disposal facility either directly
or via an approved waste receptacle and collection service. Storage areas are to be located near the
temporary access to the site so that access can be gained with out damage to infrastructure.
45. All building materials containing asbestos products must be disposed on in accordance with industry best
practice.
46. A temporary crossing must be provided to protect road reserve infrastructure including kerb and channel;
47. Any damage to footpaths, street plantings, kerb and channel or roadways at the removal site, the
relocation site or between the sites must be repaired or reinstated to at least pre-existing conditions.
48. Sediment and erosion control measures must be placed on site prior to the works commencing and shall
be maintained until all works are complete. The erosion and sediment control measures shall be in
accordance with the “Best practice guidelines for control of stormwater on building sites” prepared by
Healthy Waterways (copy attached or available at www.healthywaterways.org).
49. All disturbed areas must be revegetated or otherwise stabilised at the completion of the works. Disturbed
areas are revegetated using species identified in PSP3 – Landscaping Plants and Guidelines.
50. The transportation of all materials to and from the site must be undertaken in a manner such that no
particle matter escapes onto a public road. All vehicles carrying out materials either to or from the site
shall be covered to prevent materials including dust being windblown from the vehicle.
51. A Waste Management Plan shall be submitted for the demolition to the Land Use Section of Noosa
Council, prior to the development permit for building works being issued. The Plan shall contain the
following information:-
MATERIALS ON-SITE DESTINATION
Re-use and Recycling Disposal
Expected waste Estimated volume (m³) On-site *specify Off-site *specify *Specify contractor
materials proposed reuse or contractor & & landfill site
onsite recycling recycling outlet
methods
Excavation material
Green waste
Bricks
Concrete
Timber – please
specify
Plasterboard
Metals – please
specify
Asbestos
Other – please
specify
NOTE: Details of site area to be used for onsite separation, treatment and storage (including weather
protection) shall be provided on the plan drawings accompanying your application.
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@e80859de\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original