NOOSA COUNCIL IDAS Development Application Decision Notice                                                          5


27.    All site stormwater drainage shall be by means of a gravity system.
Sewer Mains
28.    The site shall be connected to Council’s existing sewerage system in Seaview Terrace via a pump up
       system. All effluent waste flows from the developed site shall be directed to an internal pump well.

29.    The sewer pumping system shall have minimum a 12 hour storage capacity between alarm and overflow
       levels .The system is to be connected to a 24 hour monitoring service which is notified in the event of a
       high level alarm. The system shall be designed to ensure that the pressure main has less than a one
       hour detention time to prevent odor production including during occupant absences. A flushing system
       may be required to ensure detention times do not exceed one hour. Engineering plans for the sewer
       layout and the sewer pumping system shall be submitted to Council for approval prior to the Plumbing and
       Drainage Application. Any enquires in relation to this matter can be directed to Mike Froude (Tel
       54495288) of Council’s Sewer Section.

30.    The site shall be connected to Council’s existing sewerage reticulation systems and be constructed in
       accordance with Council’s standards and requirements at no cost to Council.
Town Water Supply
31.    The site shall be connected to Council’s existing town water supply and be constructed in accordance with
       Council’s standards and requirements at no cost to Council.

32.    All water meters must be located outside the property boundary and in an easily assessable location to
       facilitate unhindered reading by Council and/or Council’s contracted water meter readers, and not behind
       fences or locked gates.
Earthworks
33.    Earthworks carried out on site shall not affect the structural integrity of any of the existing fences or
       structures that border the development site. Fences that are affected shall be replaced prior to the
       Building Certifier issuing the Certificate of Classification. In this regard any fences to be replaced shall be
       clearly shown on the plans submitted for Operational Works approval.
Site Stability
34.    A Geotechnical Engineer or similar qualified expert shall assess the soil condition on site, determine the
       soil classification, establish whether any measures are required to protect the stability of adjoining
       buildings and/or structures and/or land, and make recommendations on the type of foundation system(s)
       best suited for the proposed development. The recommendations of this report shall be incorporated into
       the design and construction of the proposed development.

35.    All foundations and supporting structures, including construction devices, shall be located wholly within
       the subject site and shall have no detrimental affect on the adjoining buildings and/or structures and/or
       land.
Erosion and Sediment Control
36.    Any person acting on this permit shall prevent erosion and sediment export from leaving the site. Site
       control measures such as silt fencing, controlled gravel access to the site and controlled disposal of
       waste, will be necessary.
      In this regard plans detailing the methods of controlling erosion and sediment are required to be submitted
      to the Council for approval prior to obtaining a Development Permit for Operational Works.
General
37.    For the following classes of work associated with development, a Development Permit for Operational
       Works must be obtained prior to commencement of works relating to that class of work. The application
       may combine any or all of these classes of work:-
       37.1. Access.
       37.2. Stormwater Drainage.
38.    Any damage caused to any public utility during the course of construction shall be repaired to Council’s
       standards and at no cost to Council.

39.    Any alteration of any public utility or other facilities necessitated by the development of the land or
       associated construction works external to the site shall be at no cost to Council.

40.    The transportation of all materials to and from the site shall be undertaken in a manner such that no
       particle matter escapes onto a public road. All vehicles carrying materials either to or from the site shall
       be covered to prevent materials including dust being windblown from the vehicle.




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@e80859de\@[email protected]
Log in to download the original file

Attachment C - 2007 decision notice.pdf · 100 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.