Original source · versioned page text
Appendix Q - Planning Scheme Code Responses
TRANSPORT, ROADS AND DRAINAGE CODE
Performance Criteria and Acceptable Solutions
PROBABLE SOLUTIONS COUNCIL USE
PERFORMANCE CRITERIA SOLUTIONS* COMMENTS
(IF CODE ASSESSABLE) ONLY
(d) maximise on-site stormwater retention S6.2 ✓ S6.2 Complies
and retardation; and As Constructed data is submitted in See Appendix G – Stormwater Management
(e) convey run-off to stormwater drainage accordance with Section 6 of PSP5 Report.
in a manner that allows roads to be Engineering Design Standards – Roads,
trafficable in Q100 ARI local rainfall Drainage and Earthworks; and
events.
S6.3 ✓ S6.3 Complies
Stormwater drainage planning, design See Appendix G – Stormwater Management
and construction is in accordance with the Report.
Queensland Urban Drainage Design
Manual.
O7 S7.1 ✓ S7.1 Complies
Roads and stormwater drainage Roads and stormwater drainage Proposal will comply.
infrastructure is constructed— infrastructure is constructed in
(a) in accordance with appropriate accordance with—
engineering standards; and (a) Sections 2, 3 and 4 of PSP5
(b) to minimise adverse environmental Engineering Design Standards –
impacts, including from run-off and Roads, Drainage and Earthworks;
erosion. (b) Queensland Design Code for
Residential Streets;
(c) AUSTROADS; or
(d) A combination of the principles in
these documents; and
S7.2 ✓ S7.2 Complies
Erosion and sediment control measures Erosion and sediment control measures will be
are designed and implemented in implemented in accordance with the appropriate
accordance with the Institution of standards.
Engineers Australia (Queensland
Division) Soil Erosion and Sediment
Control - Guidelines for Queensland
Construction Sites.
Environmental Protection ✓ S8.1 Complies
O8 S8.1 Proposal will comply.
Roads and stormwater drainage Roads and stormwater drainage follow the
infrastructure are located and aligned so edge of existing disturbed areas, or
as to— alternatively, these works are co-located
1 Solution: ✓ = Acceptable Solution
A/S = Alternative Solution Cooroy Care Farm
N/A = Not applicable to this proposal
521 Elm Street and 10-22 Rose Gum Road, Black Mountain Commenced 3rd February 2006 - Updated October 2006 Page 4